My RFI hasn’t been answered
Contractor side: Communications
Where the contract stands
"RFI" is not an NEC term, so it depends what you are really asking. If the contract requires a reply, 13.3 sets the period and a late reply can be a compensation event under 60.1(6), but only where it has a real effect. Give an early warning if the delay could matter, and remember the eight weeks in 61.3 run from when you knew the reply had been missed.
Read the guide: RFI with no response
This is our plain-English summary, not legal advice. Your own contract, including any Z clauses, decides.
In Contract Status, step by step
See it on the register
The RFI register shows priority, status, the date required and how many replies it has had.

RFI-0003 and RFI-0004 are both overdue here.
Open it: whose move is it?
The record says the answer is overdue and that it is waiting for the Client. You can add information without closing it, or close it if it is no longer needed.

RFI-0003 from the contractor side.
Move it to the right register if it matters
An RFI does not notify anything. If the wait could affect price or programme, add an early warning. If a missed reply has had a real effect, add a compensation event, with the date you knew.

From the contractor side: the Add buttons you have on this contract.
Worth knowing: the date on an RFI is a management date. Contract health can show it Amber, never Red, because an RFI does not itself notify anything under the contract.
All screens are from the upgraded app, using a fictional water company, Kestrel Valley Water, and its made-up contractors.
What happens next on the other side
The Client side has the RFI on its Action List with an Answer button. An answer closes the RFI; asking for clarification keeps it open. It can be reopened within 14 days.