Skip to content
Book a demo

See it working

Each page here takes a question people really ask on an NEC contract, sets out the contract position in plain English, then shows how you would handle it in Contract Status, screen by screen.

Every screen is from the upgraded app, using a fictional water company, Kestrel Valley Water, and its made-up contractors. Where the app stops and your judgement starts, the page says so. Contract Status records what the two sides did and when; it does not decide who is right.

Contractor side

If you are the Contractor

Warning, notifying, quoting and keeping your position when replies are late.

Early warnings and compensation events

IFC drawings are late: warn first, then notify

Warn now, then notify the compensation event separately with the date you became aware.

Compensation events

The Project Manager has not replied to my notification

Give notice that the reply is late, watch the two weeks, then record deemed acceptance.

Compensation events

Keeping inside the eight-week time bar

Record the date you became aware. The record shows how long you took, and says so if it passed eight weeks.

Quotations

My quotation is waiting for a reply

The reply date is on the record. Give notice, then record deemed acceptance when the time is up.

Compensation events

Exceptional weather: notifying the event

Put the recorded figure and the one-in-ten value on the notification, with the clause and the date.

Compensation events

Unexpected ground conditions

Warn, notify under 60.1(12), then follow it to the quotation or the Project Manager's assessment.

Compensation events

A service that isn't on the drawings

Record what you found, when you knew and the clause, then quote on the event.

Programme

My programme has not been accepted

Read the reason on the record, answer the revised programme request and keep the trail.

Payment

The payment certificate came in lower than we applied for

See applied against certified, ask for the reasons in writing, and get the next application in on time.

Defects

The Supervisor has notified a Defect

Reply on the record with the fault, cause and action, or say why you disagree.

Communications

My RFI hasn't been answered

The RFI shows Overdue and whose move it is. If it matters, raise it on the right register.

Subcontracts

A subcontractor's notice that affects the main contract

The subcontract has its own register. Passing it up to the main contract is your separate notice.

Compensation events

The Project Manager has rejected my compensation event

The decision and the reason stay on the record, with who replied and when.

Instructions

An instruction came with no compensation event

Follow the instruction, then notify the event yourself and quote the instruction reference.

Instructions

The Project Manager has told us to stop work

The stop is on its own record with its clause. The restart and the event follow it.

Tests and inspections

A test has failed: who pays for the repeat?

The result, the Defect, the repeat and the cost of the repeat are linked on one record.

Early warnings

Nobody has responded to my early warning

Ask for the meeting from the register, then the decisions and actions go on record.

Client side

If you are the Client, Project Manager, Supervisor or PMO

Replying on time, deciding on change and seeing where every contract stands.

On site

The same records on a phone

Registers, records and the Action List work at phone width, so the site team can see where a notice stands and what the next step is.

  • The next step is the main button on each record
  • Register rows become blocks you can read on a small screen
  • The banner explains a late reply in plain words
The Action List at phone width with a tile for each register

See it on a contract you can click through

The guided tour lets you walk the same fictional account yourself. Or book a demo, and bring the situation you are dealing with.