The NEC adjudication procedure under Option W2 starts with a notice of adjudication, moves to a referral within seven days, and normally ends with a decision within twenty-eight days of that referral. This is the procedure for contracts covered by the UK's Housing Grants, Construction and Regeneration Act 1996, which covers most UK construction work.

The steps below follow W2 in the NEC4 subcontract text, with NEC3's W2 very similar. For the other routes, see NEC disputes and termination.

The steps

StepWhoWhen
Notice of adjudication, briefly saying what the dispute is and what decision is wantedThe referring Party, copied to a named AdjudicatorAny time
Confirm able to act, or resignAdjudicatorWithin 3 days of receipt
Nomination, if no one is named or the named person can't actParties jointly or the nominating bodyWithin 4 days of a request
Refer the dispute, with supporting information, and copy it to the other PartyThe referring PartyWithin 7 days of the notice
Further information from a PartyEither PartyWithin 14 days of the referral, unless extended
Decision with reasonsAdjudicatorWithin 28 days of the referral, unless extended
Correct clerical or typographical errorsAdjudicatorWithin 5 days of the decision
Notify intention to refer to the tribunalA dissatisfied PartyWithin 4 weeks of the decision being notified

Periods given in days don't count bank holidays, Christmas Day or Good Friday. The decision period can be extended by up to 14 days with the referring Party's consent, or by any period both Parties agree.

A worked timeline

A fictional dispute about the assessment of a compensation event. Dates are illustrative, and ignore any bank holidays.

DateWhat happens
Mon 2 MarchContractor gives notice of adjudication, copied to the named Adjudicator
Thu 5 MarchAdjudicator confirms it can act
Mon 9 MarchContractor refers the dispute, with its supporting documents
Mon 23 MarchClient's further information is due
Mon 6 AprilDecision due, 28 days from the referral
Mon 13 AprilWhere the decision alters a sum notified as due, the new sum falls due 7 days after the decision (NEC4 subcontract text; NEC3 uses the later of that date and the final date for payment)
Mon 4 MayLast day to notify the tribunal, if the decision was given on 6 April

In a real case, check bank holidays, which would move several dates in this example. Agree in advance who's counting.

The Adjudicator's powers

  • Look again at what the Project Manager or Supervisor did, or didn't do, on the disputed matter, and change it.
  • Alter a matter treated as accepted or correct, such as a treated-as-accepted quotation.
  • Look into the facts and the law on its own initiative.
  • Instruct a Party to provide more information or take other action, within a stated time.
  • Carry on and decide on what it has, if a Party doesn't comply.
  • Allocate its own fees and expenses in the decision.

Additional cost or delay to the Contractor in a decision follows the compensation event assessment rules. So a claim should be built on Defined Cost and the Accepted Programme, not on a general claims approach. See assessing compensation events.

If a decision is late

The Parties and the Adjudicator can agree more time. If they don't, either Party can treat the Adjudicator as having resigned. A decision that arrives late raises legal questions, so take advice if it happens.

What makes a good referral

  1. One clear question and the precise decision you want, in the same words as the notice.
  2. A chronology with document references.
  3. The contract's clauses, cited by the correct edition.
  4. Calculations someone else can follow.
  5. Evidence: programmes, records and statements. Short and well-organised beats long and vague.

The notice defines what's being decided, so don't draft it loosely. The 7-day referral period is short, and most of the work should already be done before the notice goes out.

Being on the receiving end

Fourteen days for further information is tight, and it may come at a difficult moment. Assign someone immediately, gather the record, and if you need more time, ask early: the period can be extended only if the Adjudicator and the Parties agree. Don't ignore the process, because the Adjudicator may then decide without your input. Our page on the role of the Adjudicator gives more background.

Other points

  • Subcontract link. Where the same matter arises under a subcontract, W2 has joining provisions, with the necessary consents. See ending an NEC subcontract for the related subcontract rules.
  • W1 is different. The steps and time bars aren't the same. See Option W1.
  • Enforcement. The decision binds as a contractual obligation, and isn't an arbitral award. Take legal advice on what enforcement involves in practice.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the client role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.