Skip to content
Book a demo

Assessing a Compensation Event: Clause 63

NEC clause 63 sets the rules for assessing a compensation event. The Prices change by the event's effect on three things: what work up to the dividing date actually cost (Defined Cost), the forecast Defined Cost of what remains, and the Fee that follows from both. It's about the event's effect, not about what the same work would have been priced at in the tender.

Those rules apply whoever does the assessment, so both quotations and the Project Manager's assessments follow them. The clause numbers below are for NEC4 ECC, with NEC3 ECC shown alongside. See the compensation events guide for the wider process.

The rules, clause by clause

RuleNEC4 ECCNEC3 ECC
Effect on actual and forecast Defined Cost and Fee, split at the dividing date63.163.1
Agreed rates or lump sums may be used63.2Option clauses, 63.14
A reduction in Defined Cost doesn't reduce the Prices, unless stated63.363.2
Certain changes do reduce the Prices63.4Option clauses, such as 63.10 and 63.11
Delay: how far the Completion Date and Key Dates move63.563.3
These are the parties' only rights for the event63.663.4
Assessed as if an early warning had been given, where stated63.763.5
Risk allowances63.863.6
Assumes a competent, prompt reaction and reasonable cost63.963.7
Ambiguity in the Scope: read in favour of the Party that didn't provide it63.1063.8
A Key Date Condition made wrong by a change is corrected63.1163.9

The dividing date

For an event from an instruction, notification, certificate or changed decision, it's the date of that communication. For anything else, it's the date the event was notified. Work done by that date is priced at actual Defined Cost, so records matter. Work after that date is priced as a forecast, even if the assessment is prepared later and some of the work has since been done.

That's why a late notice can change the shape of the assessment. Notifying later moves more of the cost onto actuals, and it can also change which Accepted Programme applies.

A worked calculation

A fictional sewer scheme with illustrative figures. The Project Manager instructs an extra manhole on 10 June, so that's the dividing date. The Contractor had already ordered materials for the original design before then, and they're now redundant.

ItemBasis£
Redundant order, cancellation chargeActual Defined Cost, by the dividing date2,400
People for the manholeForecast11,000
EquipmentForecast6,500
Plant and MaterialsForecast9,100
Risk allowance: 30% chance of a further pump for 2 weeksForecast1,000
Effect on Defined Cost30,000
Fee at an illustrative 10%Fee percentage from the Contract Data3,000
Change to the Prices33,000

If the forecast later proves too low or too high, the assessment normally stays as it is. That's the deal: the Contractor takes the risk on a forecast in return for a quick answer. See implementing a compensation event.

Risk allowances

The assessment includes allowances for matters with a significant chance of occurring. In NEC4 the test is that the matter isn't itself a compensation event; in NEC3 it's that the matter is at the Contractor's risk. More on this in risk allowances under NEC. If the effects are too uncertain to forecast fairly, the Project Manager states assumptions instead (61.6), and a later correction is a new event, 60.1(17).

Reductions

The default is that a saving doesn't reduce the Prices. The exceptions are specific: an instruction changing the Scope that saves money, unless the change is one the Contractor proposed and the Project Manager accepted, in which case the Options deal with it; and a corrected assumption. In NEC4 the Options A and B treatment uses a value engineering percentage, while the target Options leave the Prices unchanged, so the saving goes through the share. Check the wording for your main Option.

Common arguments

  • "Use the bill rates." Not unless both agree. The standard basis is Defined Cost and Fee. See what Defined Cost is.
  • "You could have done it cheaper." Clause 63.9 assumes the Contractor reacts competently and promptly and that costs are reasonably incurred. That's a fair challenge, but it should identify what a competent reaction would have been.
  • "That cost is Disallowed." Disallowed Cost is a payment concept in the cost-based Options. It's not the same test as this assessment, and the two shouldn't be mixed.
  • "The Fee shouldn't apply." It does. The fee percentage is applied to the effect on Defined Cost. See the Fee.

How this looks in Contract Status

The quotation date has passed, and the record offers the Project Manager's assessment.

The quotation date has passed, and the record offers the Project Manager's assessment. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.