Compensation Event vs Relief Event

A compensation event gives both time and money, where the event affects each. A relief event, in the contracts that use the term, usually gives time or protection from a contractual remedy, but no money. Standard NEC ECC has no relief events: every listed event goes through the same compensation event process, whatever its cause.

So if someone on an NEC job talks about relief events, they are either using language from another contract or referring to something added by amendment. For the NEC side, see the compensation events guide.

What each gives

Compensation event (NEC ECC)Relief event (typical usage elsewhere)
More timeYes, if planned Completion or a Key Date is delayedUsually
MoneyYes, on the effect on Defined Cost plus FeeUsually no
Protection from delay damages or terminationIndirectly, because the Completion Date movesUsually the main point of it
Who carries the costClient, for the change assessedEach side tends to carry its own
Where the term comes fromThe NEC contracts themselvesOther forms and bespoke contracts; the meaning depends on the document

The right-hand column is only a generalisation. A relief event means whatever its contract says it means, so read the definition in the document you are working with.

Why NEC does it differently

JCT users are familiar with a similar split, between grounds for more time and grounds for loss and expense. Under NEC there's one list, and each event on it gives both effects if the facts support them. That fits the broader design: one route, one assessment, one result. The JCT and NEC comparison looks at that in more detail.

The most striking example is 60.1(19), the prevention event. Force majeure wording in other contracts often gives time only. Under NEC, an event that neither Party could prevent, and that an experienced contractor would have thought too unlikely to allow for, is a compensation event with both time and money. There's more on this in the guide to force majeure under NEC.

Where a time-only rule can appear in NEC

Clients can and do change the default position, usually by a Z clause. Things to look out for:

  • A Z clause saying certain events, such as weather or utility delays, give a change to the Completion Date but no change to the Prices.
  • Z clauses that delete an event from the list, for example 60.1(19), leaving the risk with the Contractor.
  • Additional events listed under 60.1(21), with restricted effects stated beside them.
  • A framework or public-sector amendment using the words "relief event" in a defined way.

Read such a clause closely. Check the process it uses too. A restricted event may still need notifying within eight weeks, and may still be quoted for and implemented as usual, with the money simply set to nil.

A worked example

A fictional eight-month job. There's a month of exceptional rainfall that passes the 60.1(13) test and delays planned Completion by two weeks. The excess-weather cost of standing crews comes to an illustrative £70,000 plus Fee.

BasisTimeMoney
Unamended NEC4 ECC2 weeks£70,000 plus Fee
Same contract with a Z clause making weather time-only2 weeksNil
Same contract with 60.1(13) deletedNoneNone; the risk stays with the Contractor

The same rainfall has three different outcomes, depending only on the contract. It's worth raising this at tender stage: the Contractor needs to price the risk it's being given, and the Client should know what it's paying for. See risk allocation under NEC.

Practical advice

  • On an NEC job, use NEC's words. A notice claiming a "relief event" may confuse matters. Cite the 60.1 sub-clause.
  • If your subcontract is a different form from the main contract, compare the two. A main contract event with money may sit above a subcontract giving only time, and you'd want to spot that before you sign.
  • Check the full NEC4 list against your contract's amendments at the start of the job, and brief the team on what's changed.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.