Skip to content
Book a demo

Keeping a Compensation Event Register

A compensation event register is a single list of every event on the contract, showing where each one stands, what's due next and what it's worth. NEC doesn't require one, unlike the early warning register, but disagreements about time bars and treated acceptance usually come down to dates that a good register would hold.

Either side can keep it, and many jobs have one on each side, which then gets reconciled at regular intervals. For what the register is tracking, see the compensation events guide. For registers in general, see the NEC registers guide.

Fields to hold

FieldWhy it's there
Reference and titleUsed in every letter
Sub-clause, such as 60.1(5)For reporting by cause, and checking entitlement
Notified bySets which route applies
Date of awarenessStarts the eight weeks under clause 61.3
Date notifiedSets the dividing date for most events
Related instruction or early warningLinked evidence, and a dividing date for instructed events
Project Manager's decision and dateOne week from notice, unless extended
Quotation instructedStarts the three weeks
Quotation submitted, and revision numberStarts the two-week reply
Reply and dateAccepted, revise or assess
Failure notified and dateStarts the further two weeks towards treated acceptance
Assumptions and 61.5 statementAffects the assessment
Quoted and implemented valueReporting and forecasts
Delay in days, Key Dates movedKeeps track of the Completion Date
Implemented dateCloses the event
Next action, owner and due dateWhat actually gets people moving

Statuses

A small set of statuses keeps reporting honest. These work for most jobs, although they're ours and not a contract requirement:

  1. Potential. Spotted, not yet notified. Keep the awareness date.
  2. Notified. Awaiting the Project Manager's decision.
  3. Not a compensation event. Closed by decision, with reasons. Note any dispute.
  4. Awaiting quotation. Instructed and on the Contractor's clock.
  5. Quotation with the Project Manager. On the Project Manager's clock.
  6. Revising. Back with the Contractor.
  7. Project Manager assessing. Under clause 64.
  8. Implemented. Closed, with a value and any change in dates.

Add a separate flag for "failure notified" rather than a status, since an event can have that flag at more than one stage.

Dates to calculate automatically

  • Date of awareness plus 8 weeks: last safe day to notify.
  • Notified date plus 1 week: decision due.
  • Instruction date plus 3 weeks: quotation due.
  • Submission date plus 2 weeks: reply due.
  • Failure notice date plus 2 weeks: treated acceptance arises.

The periods above are the standard ECC ones under clause 62.3 and its neighbours. Change them if your contract amends them or uses another form. A spreadsheet can handle this on a small job; the guide to spreadsheet tracking explains where it starts to fail. Contract Status is one example of a system that handles these dates and records.

A sample line

RefClauseStatusNotifiedNext actionDueValueDays
CE-02260.1(3)Quotation with the Project Manager4 MayReply (PM)12 June£38,5005

This fictional line tells a reader everything needed in a single glance. It's a good target for how much detail a summary view should have.

What to report

Keep the monthly report to the things that lead to a decision:

  • Count and value of events by status, showing what's still unimplemented.
  • Implemented total against the original Prices, and the current Completion Date.
  • Overdue items, by who holds them.
  • Oldest open event, and average days from notice to implementation.
  • Events by cause, which shows recurring problems such as late design information.
  • Forecast value of potential and unimplemented events, for the Client's budget.

Reconcile the two parties' registers at regular meetings. A disagreement over whether an item is on the register at all is far better found now than at final account stage. The guide to NEC reporting has more ideas.

How this looks in Contract Status

A contract at a glance: time, the total of the Prices, payments and replies waiting.

A contract at a glance: time, the total of the Prices, payments and replies waiting. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.