Skip to content
Book a demo

Compensation Event Flow Chart Explained

An NEC compensation event flow chart comes down to six decisions, each with a time limit and only a few possible outcomes. This page writes that chart out as a set of questions, so that you can follow it from any point and see where each answer leads. It uses NEC4 ECC, with its standard periods.

The same periods apply to NEC3 ECC. NEC3 has clause 65 for implementing, and clause 61.1 for the instruction to quote. Any Z clauses in your contract take priority. The process guide tells the same story in prose, and the compensation events guide is the starting point.

Decision 1: who should notify?

IfThen
It arises from an instruction, notification, certificate or changed decision of the Project Manager or SupervisorThe Project Manager notifies at that time (61.1) and instructs quotations (61.2). Go to decision 3
Anything else, or the Project Manager hasn't notifiedThe Contractor notifies, within eight weeks of becoming aware (61.3). Go to decision 2

Decision 2: does the Contractor's notice qualify?

The Project Manager has one week, or longer if agreed, to apply the tests in clause 61.4.

AnswerNext
No: fault, not happening, too late, no effect, or not on the listPrices and dates stay. Reasons given. Contractor can use the dispute route
YesQuotations instructed. Go to decision 3
No replyContractor may notify the failure. Two further weeks of silence is treated as a yes, with quotations instructed

Decision 3: what goes in the instruction?

This isn't a yes or no. The Project Manager considers three questions as it instructs:

  • Could an experienced contractor have warned? If so, say so (61.5).
  • Are the effects too uncertain to forecast? If so, state assumptions (61.6).
  • Are there practical alternatives? If so, discuss them, and consider asking for alternative quotations (62.1).

Decision 4: did the Contractor quote in time?

AnswerNext
Yes, within three weeks (or an extension agreed beforehand)Go to decision 5
NoThe Project Manager assesses it (64.1). Go to decision 6

Decision 5: how does the Project Manager reply?

It has two weeks from submission (62.3).

ReplyNext
AcceptanceImplemented
Instruction to submit a revised quotation, with reasonsThree weeks. Back to decision 4
Will make its own assessmentGo to decision 6
No replyContractor may notify the failure. Two further weeks of silence is treated as acceptance. Implemented

Decision 6: did the Project Manager assess in time?

AnswerNext
Yes, within the quotation period from when the need became apparent (64.3)Assessment notified. Implemented. Contractor can dispute it
NoContractor may notify the failure. Two further weeks of silence: its quotation is treated as accepted (64.4). Implemented

The end point

There are three ways to reach implementation: acceptance, the Project Manager's assessment or treated acceptance. All three lead to the same place under 66.1. The Prices and dates change, and the assessment is not normally reopened.

Reading the chart

Three things stand out once it's written like this:

  • There's no dead end for the Contractor. Every stage has a way forward if the other side stays silent, provided the Contractor gives notice.
  • The only way out before quotation is the 61.4 decision. After that, the question is what the event is worth, not whether it counts.
  • Treated acceptance isn't automatic. In each case, an action by the Contractor is required to start it.

Drawing your own

If you want to draw one for your team, use two lanes, for the Project Manager and the Contractor, with the decision numbers above as the shapes and each period written on the arrow. Add your own contract's amended periods and any Z clause steps, such as a Client approval level. Pin it near the people who hold these clocks, and use it alongside the full list of NEC time periods.

How this looks in Contract Status

The record shows the date you became aware and how long you took to notify.

The record shows the date you became aware and how long you took to notify. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.