A Table of Key NEC Time Periods

The key NEC time limits are eight weeks to notify a compensation event, one week to reply to it, three weeks to quote, two weeks to reply to a quotation and two weeks to answer a programme, all under the Engineering and Construction Contract (ECC). The tables below set these out for NEC4 ECC, NEC3 ECC and the NEC4 subcontract (ECS).

They show the unamended forms. Z clauses often change them, and some figures are for your Contract Data, so treat this as a starting point and overwrite it with your own. To use them on a live job, see tracking periods for reply, or return to the guide to managing NEC contracts.

Compensation events

StepNEC4 ECCNEC3 ECCNEC4 ECSClause
Contractor notifies an event8 weeks8 weeks7 weeks61.3
Reply to a notified event1 week1 week2 weeks61.4
After notice of that failure, further silence before treated as accepted2 weeks2 weeks3 weeks61.4
Submit a quotation3 weeks3 weeks2 weeks62.3
Reply to a quotation2 weeks2 weeks4 weeks62.3
Submit a revised quotation3 weeks3 weeks2 weeks62.4
Quotation failure: further silence2 weeks2 weeks3 weeks62.6
Project Manager's own assessmentThe time allowed for a quotationThe time allowed for a quotationThe time allowed for a quotation64.3
Assessment failure: further silence2 weeks2 weeks3 weeks64.4

A reply to a quotation for a proposed instruction works differently under NEC4: it comes by the date the Project Manager stated when asking (65.2). Under NEC3 it follows the normal two weeks. See NEC4 proposed instructions.

Programme and early warnings

StepNEC4 ECCNEC3 ECCNEC4 ECSClause
First programmeContract DataContract DataSubcontract Data31.1
Reply to a programme2 weeks2 weeks3 weeks31.3
Programme failure: further silence before treated as accepted1 weekNo such rule2 weeks31.3
Revised programme when instructedPeriod for replyPeriod for replyPeriod for reply32.2
Regular revised programmeContract Data intervalContract Data intervalSubcontract Data interval32.2
First register1 week from the starting dateNo fixed period1 week from the subcontract starting date15.2 (NEC3: 16)
First meeting2 weeks from the starting dateNo fixed period2 weeks from the subcontract starting date15.2
Register updated after a meeting1 weekNo fixed period1 week15.4 (NEC3: 16.4)

There is no set date for an early warning itself beyond doing it as soon as you become aware. NEC sets no period for replying to a warning, so any target for that is your own.

Payment and final account

StepNEC4 ECCNEC3 ECCNEC4 ECSClause
Payment certificate after the assessment date1 week1 week2 weeks51.1
Payment after the assessment date, unless the data says otherwise3 weeks3 weeks4 weeks51.2
Pay less notice (Option Y(UK)2)7 days before the final date for payment7 days before the final date for payment7 days before the final date for paymentY2.3
Final assessment after the Defects Certificate4 weeksNone4 weeks53.1
Final assessment after a termination certificate13 weeksNone14 weeks53.1

The dates for payment under Y(UK)2 work differently from the certificate clock. See the NEC payment timeline for how they fit together.

Completion and other periods

StepPeriodClause
Certify Completion1 week after Completion30.2
Take over the works, if the Client doesn't opt out2 weeks after Completion, at the latest35.1
Certify take-over of a part1 week after take-over35.3
Quality policy statement and quality plan (NEC4)Contract Data40.2
Correct a DefectDefect correction period in the Contract Data44.2 (NEC3: 43.2)
Any other reply requiredThe period for reply in the Contract Data13.3

Reading this table properly

  • Not every form uses these. The professional service and term service forms have their own Contract Data and may use different figures, and the short forms differ more. Look up your own form rather than assuming.
  • Disputes are not shown. Those periods depend on whether Option W1 or W2 applies. See time limits for disputes.
  • Termination is not shown. Those periods vary between editions and forms, so read your own clause 91 and see the termination procedures page.
  • Extensions are possible for many of them, but only by agreement before the reply is due (13.5, 62.5), and not for all. The Contractor's eight weeks under 61.3 isn't one of those a Project Manager can simply extend.

How this looks in Contract Status

My Dashboard: what is waiting on you and which replies you owe.

My Dashboard: what is waiting on you and which replies you owe. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Get free NEC templates, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.