NEC Templates: A Practical List

The NEC templates that most jobs need are an early warning notice and register, a compensation event notice and quotation, an instruction, a programme submission note and a set of short reply letters. This page lists them by who uses them and when, with links to each, all in our own wording rather than NEC text.

Use them as a starting point. Your Scope or Client may require its own forms, and Z clauses can add content that a notice has to include. For the routines they support, see managing NEC contracts. The clause numbers on them assume the NEC4 Engineering and Construction Contract (ECC), so change them if you are on another form.

Templates by task

TaskTemplateWho uses it
Warning about a problemEarly warning noticeProject Manager, Contractor
Tracking warningsEarly warning registerProject Manager keeps it
Notifying a compensation eventCompensation event noticeContractor, Project Manager
Pricing an eventQuotationContractor, or Project Manager for its own assessment
InstructingProject Manager instructionProject Manager
Submitting a programmeProgramme submissionContractor
Reviewing a programmeProgramme review checklistProject Manager
Replying, reminding, extendingLetter templatesAll
Tracking eventsCompensation event registerBoth sides, shared
Tracking everything elseRegister fields listBoth sides

Set-up order on a new contract

  1. Before the starting date: Agree the numbering, and create the empty registers. Adapt the headers to your project and put the actual reply periods into the letters.
  2. Week 1: Have the early warning register and meeting notes ready, since NEC4 has dates for them (15.2).
  3. By the first programme date: Prepare the programme note and checklist.
  4. By the first likely event: Have the compensation event notice and quotation sheet in the hands of whoever will use them, including site managers. Give site teams a simple "tell the commercial team today" prompt.
  5. By the first assessment date: Settle the application and certificate formats. See payment applications.

Templates by stage of the event

A compensation event alone can use five documents. This is how they follow on from one another.

StageDocumentClock
Something might happenEarly warning noticeAs soon as aware (15.1)
It has happenedContractor's notice8 weeks from awareness (61.3)
Reply61.4 reply letter1 week
Price itQuotation and any revised programme3 weeks from the instruction (62.3)
DecideAcceptance, revision instruction, or notice of own assessment2 weeks (62.3)

What to watch when adapting a template

  • Form and edition. Role names, clause numbers and periods all shift. An NEC4 template on an NEC3 job looks careless and could cite the wrong rule: early warnings are at 16 in NEC3 ECC and 15 in NEC4, for example.
  • Periods in the template body. Don't hard-code them unless you've checked the contract. The subcontract has different ones. See NEC time periods.
  • Automatic text. A standard paragraph saying "this is without prejudice" or reserving all rights may conflict with the tone of mutual trust you need, and adds little in most routine notices.
  • Too many versions. Keep one controlled master in one location. Three teams with three versions will drift.
  • Copying from elsewhere. NEC's text is copyright. Short clause references are the safe way to point at the contract. Don't paste clauses in.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Get free NEC templates, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.