Skip to content
Book a demo

Early Warning Register Template

An early warning register template needs only two things to satisfy the contract: a description of each matter, and how its effects will be avoided or reduced. The extra columns below make it workable, because they show who is doing what by when and what has already been decided.

You can build this in a spreadsheet in a few minutes. It suits the NEC4 Early Warning Register and the NEC3 Risk Register alike. Just change the title and the clause references.

The columns

ColumnWhat to enterStatus
ReferenceA unique number that matches the notice, such as EW-017. Use "CD" for matters from the Contract DataGood practice
Date enteredThe date the matter was notified or addedGood practice
Raised byProject Manager, Contractor or Contract DataGood practice
Description of the matterOne or two plain sentences that someone new to the job could followRequired
Possible effectMark each that applies: Prices, Completion, Key Date (name it), performance, Contractor's costGood practice
Rough scaleA range or "not yet known". Leave out private pricingOptional
How effects will be avoided or reducedThe agreed response, updated after each meetingRequired
Action ownerA named person, not a company or teamGood practice
Action dateA real date, not "ongoing"Good practice
Latest decision and meeting dateWhat the last meeting decided, with its dateGood practice
Instruction referenceAny Scope change instructed with the revised registerGood practice
Linked compensation eventThe event reference, if the matter became or led to oneGood practice
StatusOpen, or Removed, with the date and meeting that removed itGood practice

Sample entries

These entries come from a fictional rail depot project. They show a level of detail that is enough without being a report.

RefMatterEffectHow avoided or reducedOwner and dateStatus
CD-01Track access for crane lifts depends on the operator's possession planCompletion; Key Date 1Contractor to share lift sequence; Project Manager to confirm possessions with the operatorJ. Patel, 14 MarchOpen
EW-006Switchgear supplier reports factory delay of up to four weeksCompletionSecond factory slot being priced; temporary supply considered at last meetingR. Owen, 21 MarchOpen
EW-009Client's IT team may change the door access system specificationPrices; performanceProject Manager to confirm decision. If it changes, an instruction will followS. Hughes, 7 MarchOpen
EW-003Possible bat roost in the old storeCompletionSurvey found none. Removed by meeting 4ClosedRemoved

Three choices to make before you start

  • Who controls the master? The Project Manager revises and issues the register under 15.4 (NEC3: 16.4). Contractors can keep a working copy but shouldn't circulate a rival version.
  • Do you need scoring? Likelihood and impact scores are not a contract requirement. They can help sort a long list, but arguments over a score waste meeting time. A simple high, medium or low, or sorting by the date a decision is needed, is often enough.
  • Will you keep private notes elsewhere? Both sides see this document. Keep your contingency, margin and commercial strategy in your own internal register.

Common faults with templates

  • An effects column that only says "cost" and "time". The contract separates Prices from the Contractor's own cost and Completion from each Key Date. The distinction often matters later.
  • No link to compensation events. Without it, nobody can see if a live matter has moved into the compensation event register, or if it needs to.
  • Deleted rows. Mark items as removed instead. The record of what was known and when can matter if 61.5 is raised later.
  • No issue date or revision number. Since NEC4 expects reissue within a week of each meeting, the header needs to show the revision and date of the meeting it reflects.

If you use it for several contracts, consider how you will see across them, as explained in the guide to tracking NEC contracts in spreadsheets. The wider picture is in the NEC early warnings guide.

How this looks in Contract Status

The Early Warning Register page, with risk scores, decisions and open actions.

The Early Warning Register page, with risk scores, decisions and open actions. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the Project Manager role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.