Skip to content
Book a demo

Who Gives an Early Warning?

Under the NEC Engineering and Construction Contract (ECC), both the Contractor and the Project Manager give early warnings, and each owes that duty to the other. Early warning is a two-way obligation: a Project Manager who treats it as something only the Contractor does has misread the clause.

The rule is at 15.1 of NEC4 and 16.1 of NEC3. This page sets out who does what. The early warnings guide gives the full process.

Who does what

TaskProject ManagerContractor
Warn of matters that could affect the Prices, Completion, a Key Date or performance in useYesYes
Warn of other matters that could raise the Contractor's total costNot requiredMay choose to
Enter matters in the registerYesNo
Issue first register (NEC4)YesNo
Instruct attendance at the first meeting (NEC4)YesNo
Instruct the other to attend a later meetingYesYes
Bring other people to a meeting, if the other agreesYesYes
Issue the revised register and any Scope changeYesNo

It is unusual for a contractor to be able to instruct a project manager, but the attendance rule works both ways. A Contractor with an urgent matter doesn't have to wait to be invited.

What the Project Manager should be warning about

A Project Manager often has information the Contractor can't get. Typical matters include:

  • A likely change of mind by the Client, end user or funder.
  • Delays to anything the Client is to provide, such as access, free-issue items or information.
  • Approvals from third parties that the Client controls.
  • Other contractors working next to the Site, and any slippage on their part.
  • Concerns seen on site visits or in the Contractor's programme.

In practice, a warning from the Project Manager often leads to a better outcome for the Client than a later compensation event would. For the wider duties of the role, see Project Manager responsibilities.

What the Contractor should be warning about

The Contractor sees the work first, its supply chain and its resources. Common sources are procurement, ground and existing conditions, subcontractor capacity, and design development. The warning should come from whoever finds the problem, so site teams need to know how to pass it on and who sends the notice. A warning stuck on a foreman's phone isn't doing anybody any good.

Everyone else

RoleDuty under the ECC clause?What to do in practice
ClientNot named in the ECC clause. The Project Manager acts hereTell the Project Manager early, so it can give the warning
SupervisorNot named in the clauseTell the Project Manager of anything that could have a listed effect; attend meetings if asked
Designers (either side)Not named; they have no direct duty under the clauseReport through whoever appointed them. Their appointment may require it
SubcontractorsUnder an NEC subcontract, owed to the Contractor, not to the Project ManagerSee early warnings for subcontractors

The roles change across the suite, so check your form. In the short contracts, the warning passes directly between the Contractor and the Employer (NEC3) or Client (NEC4), since there is no Project Manager. The professional service contracts use their own role names, too.

Delegation and awareness

A Project Manager can delegate actions after notifying the Contractor, so a commercial or site representative may issue notices and the register. Make sure the Contractor knows who that is.

A harder practical question is whose awareness counts. If a junior engineer on site knew about a problem weeks before the commercial team did, the Contractor can't easily argue it was unaware. In any event, the test for reducing a compensation event looks at what an experienced contractor could have warned of. Treat knowledge anywhere in your team as your organisation's knowledge, and build a route for it to reach the person who sends notices.

If the Project Manager doesn't warn: the contract's express price consequence, in 61.5 and 63.7 of NEC4, applies only to a missed warning by the Contractor. A Project Manager's silence is still a failure to follow 15.1, and it sits badly with mutual trust and co-operation under 10.2. Whether it leads to anything further depends on the facts, so take advice on a specific case.

How this looks in Contract Status

An early warning in Contract Status, with its risks, reply date and score.

An early warning in Contract Status, with its risks, reply date and score. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the Project Manager role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.