NEC forms fall into two groups: the Contract Data and other contract documents, which NEC publishes in a set format, and the day-to-day forms for notices, certificates and registers, which you mostly need to create yourself. NEC doesn't prescribe a form for most communications, though your Scope may name a system or format.

This page lists what you need for the NEC4 Engineering and Construction Contract (ECC), who issues each one, and where to find a sample on this site. For the wider routine, see managing NEC contracts.

Forms at contract formation

DocumentWho completes itPurpose
Contract Data part oneClientSets the Options, dates, periods, people and many key values
Contract Data part twoContractorFee percentage, key people, cost rates, first programme if offered, and so on
ScopeClient, plus any Scope the Contractor provides for its own designWhat the works are, plus constraints
Site InformationClientWhat is known of the Site and its surroundings
Activity Schedule or Bill of QuantitiesContractor, as the Option needsSets the Prices
Contract form of agreementPartiesBinds the Parties. Check what your organisation uses, as many have their own form

Forms during the job

FormWho issues itClauseSample
Early warning noticeProject Manager or Contractor15.1Template
Early Warning RegisterProject Manager15.2, 15.4Template
InstructionProject Manager, or Supervisor for tests and Defects14.3 and othersTemplate
Compensation event noticeContractor or Project Manager61.1, 61.3Template
Reply to a notified eventProject Manager61.4Sample wording
QuotationContractor62.2, 62.3Template
Project Manager's assessmentProject Manager64.1, 64.3Use the quotation build-up, with reasons
Programme submissionContractor31.1, 32.2Template
Application for paymentContractor50.2See payment applications
Payment certificateProject Manager51.1Contract-specific
Pay less noticeEither Party, Option Y(UK)2Y2.3See pay less notices
Defect notificationSupervisor or Contractor43.2Sample wording
Completion certificateProject Manager30.2Date and extent
Take-over certificateProject Manager35.3Date and extent
Defects CertificateSupervisorSee Defects CertificateLists Defects, or states none
Final assessmentProject Manager (or Contractor if it isn't issued in time)53.1, 53.2See final assessment

What makes a form good enough

A form is valid if it does what the contract requires, whatever it looks like. That usually means it is readable and can be copied and kept on record (13.1), and a notification or certificate is separate from other communications (13.7). Beyond that, a good form does three things:

  1. Prompts for facts people forget, such as the date of awareness in a compensation event notice.
  2. Carries the role and clause on its face, so nobody has to ask what it is two years on.
  3. Feeds a register, with no retyping if you can avoid it.

Other forms and editions

  • NEC3 ECC: Contract Data parts are similar, with Works Information and the Employer. The final assessment isn't there, and Defects clauses are numbered differently. See NEC3 vs NEC4.
  • Short contracts: these include a pack of contract forms and Contract Data set out in a simple way. See the Engineering and Construction Short Contract.
  • Term and service contracts: you need a Task Order form and a Service Manager's versions of the above. See Task Orders explained.

Don't paste NEC clause wording into your own forms unless you have the right to. A short clause reference does the job, and our sample wording is written so you can use it freely.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Get free NEC templates, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.