NEC3 vs NEC4: The Main Differences

The main differences in NEC3 vs NEC4 are new names, moved clauses, tighter timing on early warnings, treated acceptance of programmes, simpler cost rules and a new final assessment. The approach is unchanged, so a good NEC3 team will adapt quickly, but habits and templates built on NEC3 can go wrong without anyone noticing.

This table compares the ECC: NEC3 April 2013 against NEC4 June 2017 with its later amendments. Your contract may have Z clauses, so check it. For the overview, see the NEC4 contracts guide.

Side by side: what changes in practice

TopicNEC3 ECCNEC4 ECCWhat it means for you
Trust and co-operationPart of 10.1Separate clause, 10.2Following the contract and co-operating are both clearly required
NamesEmployer, Works Information, Risk RegisterClient, Scope, Early Warning RegisterUpdate every template
Early warning timingNo fixed timesFirst register 1 week and first meeting 2 weeks after the starting date; revised register within 1 week of each meetingDiarise from day one
Contractor's saving proposalsNo clauseClause 16A formal route, with a set reply
Programme with no replyA late reply is a compensation event onlyTreated as accepted after a notification and a further week (31.3)Project Managers need to reply or risk accepting a poor programme
AccelerationThe Project Manager can instruct a quotationDiscussed first; both have to be willing before a quotation is instructed (36.1)A discussion comes first
QualityNo quality management clauseClause 40: a system, a policy statement and a planA new submission for acceptance
Applications for paymentProject Manager considers any applicationContractor applies before each assessment date (50.2); without one, it gets the lesser of the assessment and the previous amount due (50.4)A missed application can leave you without a payment
FeeDirect and subcontracted percentagesOne fee percentageTender differently
Finalising Defined CostNo process50.9, Options C to EAudit items can be closed during the job
Final accountNo procedureFinal assessment, clause 53A clear end, and a time limit to challenge it
Compensation events19 core events21: adds (20) quotation for a proposed instruction not accepted and (21) events added in the Contract DataCheck for bespoke events
AssessmentA date divides work done from work not yet done (63.1), with no labelThe same idea, now called the "dividing date" (63.1)A clearer name for the line between actual and forecast
Proposed instructions61.2 and 62.3Clause 65The Project Manager states when it may be given
LiabilitiesEmployer's risks; everything else with the ContractorClient's liabilities (80.1) and listed Contractor's liabilities (81.1)Read the new lists
Termination at willThe Employer may terminate for any reasonOnly if Option X11 is chosenA new tender decision
DisputesStraight to the AdjudicatorSenior Representatives first or by agreement, and Option W3Name your representatives
Communications systemNot addressedWhere the Scope names one, it decides when a communication takes effect (13.2)Agree how you will communicate

The clause-by-clause number moves are in the guide's renumbering table.

The three changes people underestimate

Treated acceptance of a programme

Under NEC3, a Project Manager who sat on a programme faced a compensation event for the late reply, but the programme itself was not accepted. Under NEC4, silence can make a programme the Accepted Programme, including any optimistic logic in it. Since delay is measured against the Accepted Programme, that matters to the Client. Programme deemed acceptance covers the steps.

Applications for payment

Many NEC3 teams treated applications as optional because the Project Manager assessed the amount due anyway. An NEC4 Contractor with no application gets no increase in what is due, because it receives the lesser of the two figures. For a fictional example: the amount due last month was £400,000, and the Project Manager assesses £460,000 this month. With no application, the amount due stays at £400,000, and the £60,000 moves to the next assessment at the earliest. Payment applications goes further.

Final assessment and its time limit

Clause 53 sets a final assessment, which then becomes conclusive unless someone refers a dispute in time. Teams that park a disagreement "for the final account" could lose the chance to raise it. See final assessment of the amount due.

What did not change

  • The 8 weeks for a Contractor to notify a compensation event (61.3).
  • The 3 weeks to quote and 2 weeks to reply (62.3).
  • Treated acceptance of notifications and quotations after a further 2 weeks (61.4, 62.6, 64.4).
  • Main Options A to F.
  • Option Y(UK)2's pay less notice at Y2.3, with suspension moving to Y2.5.

Common mistakes when switching

  • Citing NEC3 numbers in NEC4 letters. "Early warning under clause 16" is a Contractor's proposal in NEC4.
  • Reusing old Z clauses unchecked. A Z clause that was written around NEC3 numbers may now refer to the wrong clause or duplicate something the contract now does.
  • Pricing two fee percentages. The NEC4 Contract Data asks for one.
  • Assuming the subcontract matches. The ECS uses the same numbers but different periods, and some of its rules differ too.

If you are planning a move, moving from NEC3 to NEC4 has the practical list. To see the changes through the words, read NEC4 terminology changes.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.