The best-known NEC4 terminology change is the Scope, which replaces the Works Information in the ECC. The Employer also becomes the Client, the Risk Register becomes the Early Warning Register, and a risk reduction meeting becomes an early warning meeting. The ideas are largely the same, but the words on your letters and registers need to change.

This page lists the changes and shows where each matters. For what else changed, see the NEC4 contracts guide, and for each term in detail, the NEC definitions glossary.

The renames

NEC3 ECCNEC4 ECCWorth knowing
EmployerClientParties are now the Client and the Contractor
Works InformationScopeSame purpose: what is to be provided and any constraints
Subcontract Works InformationSubcontract ScopeIn the ECS
Risk RegisterEarly Warning RegisterClause moved from 16 to 15
Risk reduction meetingEarly warning meetingNow has a minimum frequency
Employer's risksClient's liabilitiesClause 80.1; the Contractor's liabilities are now listed too
Shorter Schedule of Cost ComponentsShort Schedule of Cost ComponentsOptions A and B
Parent company guarantee (X4)Ultimate holding company guaranteeA different entity may now be asked to give it
Partnering (X12)Multiparty collaborationRestructured
Contractor's design: reasonable skill and care (X15)The Contractor's designReasonable skill and care, with design insurance
Dispute resolution (section W)Resolving and avoiding disputesAdds W3
He, hisGender-neutral wordingNo change in meaning

New terms

TermWhat it meansFind it at
Corrupt ActA new defined term, tied to a new clause and a reason for terminationDefinitions, clause 18
Dividing dateThe line between work done and work still to do when assessing a compensation event. NEC3 has the idea without the name63.1
People RatesRates for assessing compensation events on Options A and BOptions A and B definitions, Contract Data part two
Contractor's proposalsThe route for the Contractor to suggest a Scope change that reduces what the Client paysClause 16
Final assessmentThe procedure that closes out the amount dueClause 53
Dispute Avoidance BoardA standing panel under Option W3Option W3

Terms that did not change

Don't change these by mistake: Project Manager, Supervisor, Contractor, Defined Cost, Disallowed Cost, Fee, Prices, Completion, Completion Date, Key Date, Accepted Programme, Site Information, Working Areas, Contract Data, Defect, and Defects Certificate.

Other forms use other words

Don't assume that "Scope" and "Client" apply everywhere, or that the old words have vanished:

  • The NEC3 PSC already called its requirements the "Scope", while still using "Employer".
  • The NEC4 Supply Short Contract has a "Purchaser" rather than a Client, and its index points "Goods Information" to the Scope.
  • The ECS uses Subcontract Scope, Subcontract Data, Subcontract Date and Subcontract Completion Date, and has a Client who isn't a party to it.
  • Service contracts have a Service Manager in the role the Project Manager has in the ECC.

For a full comparison of the two biggest renames, read Works Information vs Scope and Employer vs Client.

Where the old words catch people out

  • Tender documents. An NEC4 contract that says "the Works Information is in Volume 3" invites an argument about what it means. Put "Scope" in the Contract Data and in the document's own title.
  • Z clauses. A Z clause carried over from an NEC3 job could define or refer to a term that no longer exists in the contract. Search for "Employer", "Works Information" and "Risk Register" before issuing.
  • Registers and reports. A column called "Risk Register ref" isn't a contract problem, but it signals to people that the old rules still apply.
  • Letter templates. A notice citing the wrong term may still be understood, but it gives the other side a point to take.
  • Company risk registers. An organisation's risk register isn't the Early Warning Register. Keep them distinct, and keep contract matters in the contract's register. See the Early Warning Register definition.

A quick find-and-replace check

When converting a template pack from NEC3 to NEC4, a straight search isn't enough, because the numbers need checking too. Work through this short list:

  1. Replace the words listed in the first table.
  2. Check each clause reference against the NEC3 vs NEC4 comparison.
  3. Remove "he" and "his".
  4. Have someone who knows NEC4 read the result. Automated replacement can change words in ordinary sentences that should have stayed as they were, for example a "client" of your own company in a covering note.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.