The NEC4 payment timeline runs on a 21-day cycle from each assessment date. With the standard periods and Option Y(UK)2, the certificate and due date fall by day 7, the last day for a pay less notice is day 14, and the final date for payment is day 21.

Your Contract Data can change the payment period, and a Z clause can change the rest. So use the table below as a starting point, and put your own dates in it at the start of the job. It's part of the wider NEC payment and Defined Cost guide.

The sequence for a main contract

DayEventWhoSource
Before 0Application for paymentContractor50.2
0Assessment dateProject Manager assesses50.1
By 7Payment certificate, which is also the payment notice under Y(UK)2Project Manager51.1, Y2.2
7Payment becomes dueY2.2
14Last day for a pay less noticeThe Party paying lessY2.3
21Final date for paymentPayer51.2, Y2.2
Next cycleAny interest for late payment joins the next assessmentProject Manager51.2

Without Option Y(UK)2 the same cycle has only the certificate and payment steps in the contract. The Construction Act then generally still applies by its own force on UK construction work, as explained in the Y(UK)2 guide.

Main contract and subcontract together

StepECC (NEC3 and NEC4)ECS (NEC3 and NEC4)
CertificateWithin 1 weekWithin 2 weeks
Due date under Y2.27 days after the assessment date14 days after the assessment date
Last pay less notice7 days before the final date (day 14)7 days before the final date (day 21)
Final date for paymentDay 21Day 28

These are the printed periods, and each can be changed by a Contract Data or Subcontract Data entry for the payment period. Payment for NEC subcontractors shows how a main Contractor might line these up.

Worked example with dates

A fictional contract with a four-week assessment interval and an assessment date of 5 March. This calendar is illustrative, and we've assumed no bank holidays fall in the period.

DateWhat should have happened
4 MarchLatest application date
5 MarchAssessment date
12 MarchCertificate issued; payment becomes due
19 MarchLast day for a pay less notice
26 MarchFinal date for payment
2 AprilNext assessment date, with the application due the day before

Notice that the next application falls only a week after payment. On a four-week cycle, the steps overlap, so a QS will usually be running one cycle's close-out and the next one's preparation at once.

Days, weeks and holidays

Option Y(UK)2 periods expressed in days have special counting. In the NEC4 subcontract, Y2.1 excludes Christmas Day, Good Friday and bank holidays. NEC3 Y2.1 refers to the Act's own method. The core clauses use weeks, which don't have that exclusion. So around Christmas or Easter, a Y2.2 date and the three-week date in 51.2 can split apart. When that happens, plot both, and work to the earlier one for action dates.

Before the first cycle

  • Confirm the first assessment date in writing. It's no later than one interval after the starting date.
  • Read the Contract Data entries for the payment period, interval and interest rate.
  • Check for a Z clause on invoicing, as many Clients add steps, including a requirement for a VAT invoice before payment.
  • Agree who at the Client can issue a pay less notice.
  • Put a calendar in place for the whole job. It's far easier to do it once, and our list of NEC time periods will help with the others.

How this looks in Contract Status

Applied and certified figures together on one record.

Applied and certified figures together on one record. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the commercial role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.