Skip to content
Book a demo

Most NEC payment mistakes come down to a missed date, a misread defined term or a record nobody kept. They're easy to avoid, but they can be expensive because each NEC date has a specific consequence attached.

The list below follows the order of a payment cycle, using NEC4 ECC unless stated. For the background on any item, start with the NEC payment and Defined Cost guide.

Before the first payment

MistakeWhy it hurtsFix
No first programme submitted when none is identified in the Contract DataA quarter of the value of work done is held back under 50.5Plan the first programme before the first assessment date
First assessment date never confirmedThe Contractor doesn't know when to applyAsk for it in writing, and see assessment date
Contract Data periods not readThe team works to printed periods when the data says something elsePut actual dates in a calendar from day one
Ambiguous Activity ScheduleNobody can agree when an activity is completeDefine each activity with a clear end point at tender

During the cycle

MistakeWhy it hurtsFix
Applying on or after the assessment date under NEC4Clause 50.4 applies and the amount due can't riseSet an internal deadline several days earlier
Assuming the certificate is an invoice, or the reversePayment stalls because no one has sent what the Client's finance team needsAgree the paperwork route at the start
Measuring payment from the wrong dateA late-paid sum isn't spotted and interest goes uncollectedClause 51.2 counts from the assessment date, not the certificate
Forgetting a certificate that shows a negativeContractor ends up owing a payment without noticingCheck the direction as well as the figure
Writing "we deduct £X" in a pay less noticeIt doesn't state the sum considered due and could be challengedState the replacement figure and how it was calculated
Missing the pay less deadlineThe notified sum generally has to be paidCheck certificates in the first week, not the third
Correcting next month, instead of giving notice this monthThe current payment isn't reducedUse both tools for what they're for

On cost Options

MistakeWhy it hurtsFix
Treating an internal cost report as Defined CostFee costs get claimed, and the application failsKeep a separate view by schedule section. See what Defined Cost is
No proof of payment on fileCost can be removed as not justified by records, along with the Fee on itLink bank records to the ledger automatically
Charging group plant at internal ratesThe schedule looks at open market rates insteadCollect market evidence when plant arrives
Charging all of a shared manager's timeThe people section allows only a proportionKeep time records for those not based in the Working Areas
Ignoring rebatesClause 52.1 takes them off, sometimes after the amount has been paidAsk finance for a rebate list each quarter
Letting forecasts drift upwardIt damages trust, and may be reversed with a negative laterReconcile each forecast against what actually happened

At the end

MistakeWhy it hurtsFix
Leaving compensation events open until the endAgreement gets harder, and the deadline doesn't moveRun batches during the defects period. See final account
Missing the 53.3 challenge periodThe assessment can become conclusiveDiarise four weeks from the day the final assessment is issued
Forgetting half of the retentionThe X16 release after the Defects Certificate period isn't automatic in practiceCheck each later assessment shows it. See retention
Delay damages not reconciled after a Completion Date changeOverpayments are due back with interest under X7.2Recalculate after every implemented event that moves the date

A quick monthly check

Three questions take five minutes and catch most of the above:

  1. When's the next application, certificate, pay less deadline and final date, by actual date?
  2. Does the amount in the certificate reconcile to the application, line by line?
  3. Has anything in the last month changed the Prices, the Completion Date or the retention position?

A register or shared tracker, like the one discussed in NEC registers, makes these questions easy to answer. Contract Status records assessment dates and payment certificates for this reason, but a clear spreadsheet does the job if someone keeps it up to date.

How this looks in Contract Status

Applied and certified figures together on one record.

Applied and certified figures together on one record. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the commercial role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.