Disallowed cost NEC style is money the Contractor really spent but cannot recover. It applies on Options C, D, E and F, it comes off Defined Cost, and the list is short and specific. Anything not on it stays in, provided the cost fits the schedule.

The definition is at 11.2(26) of Options C, D and E in NEC4 ECC, and at 11.2(25) in NEC3 ECC. Option F has its own shorter version, at 11.2(26) in NEC3. It belongs with the rest of the NEC payment and Defined Cost guide.

The list, and what proves each item

Disallowed CostIn plain termsWhat decides it
Not justified by accounts and recordsNo paper trail, or one that doesn't support the sumThe Contractor's records
Paid to a Subcontractor or supplier when its contract didn't require itA payment beyond what its contract requiredThe subcontract terms and assessment
Incurred only because a procedure in the Scope was not followedFor example, skipping a required tender processThe Scope and the cost difference
Incurred only because a required early warning wasn't givenSee missed early warningsWhen a warning could have been given, and what it would have saved
Incurred only because notification of an adjudication or tribunal with a Subcontractor or supplier wasn't given (NEC4 only)The Project Manager wasn't toldThe notification record
Correcting Defects after CompletionThe whole cost of thisDate and cause
Correcting Defects caused by not following a constraint in the ScopeRework following a breach of a stated method or limitThe Scope and the cause
Plant and Materials not used, beyond reasonable wastageOver-ordering, unless a Scope change caused itQuantities and the wastage allowance
Resources left unused beyond reasonable availability and use, or kept after a request to remove themIdle plant and surplus peopleAllocation records and any request to remove
Preparing for and conducting an adjudication or tribunal between the PartiesYour own dispute costs on the main contractNature of the cost

The NEC4 list above is taken from the NEC4 Engineering and Construction Subcontract, whose text matches this structure, so check the wording of your own ECC. NEC3 has the same list without the fifth row.

"Only because" and other small words

Three limbs of the definition use the word "only". If the cost would have been incurred anyway, it stays in. Suppose a supplier's tender process was skipped but the price paid was the lowest available. That's a breach of procedure, but it may not have caused any extra cost.

By contrast, Defect correction after Completion is in the second group, with no causal link needed. It doesn't matter who was careless. And Defect correction before Completion, unless a Scope constraint was broken, isn't on the list at all. That's a large and often missed point: normal rework during construction generally counts as cost on these Options, and the Contractor's incentive comes through the target and share.

Who decides, and who proves

NEC3 says Disallowed Cost is what the Project Manager decides. The NEC4 subcontract removes those words and states it as cost that meets the description. In practice, the Project Manager still has to reach a view at each assessment, and either side can dispute it.

The first limb puts practical weight on the Contractor, since a cost with no records fails. For the others, the Project Manager should be able to explain why the item is caught. For example, "cost is too high" is not a reason. "This £18,000 of crane time follows your off-hire request of 3 May" is.

Worked example

A fictional NEC4 Option C job with illustrative figures. The Project Manager reviews a £20,000 crane cost.

  • Week 1 to 6: £12,000, used as planned. Stays in.
  • Week 7 to 8: £4,000, on site but unused during a planned gap. Reasonable availability, so it stays in.
  • Week 9 to 10: £4,000, after a written request to remove it. Comes out.

Defined Cost is £16,000 for the crane. Only the last two weeks are affected, and the written request does the work.

Practical steps

  • Contractor: run your own Disallowed Cost review before you apply. It's better to find a missing proof of payment yourself. Then see the open book guide.
  • Project Manager: state which limb applies, how much and why. The audit guide covers what to sample.
  • Both: agree early what "reasonable wastage" and "reasonable availability" mean for the main items. The contract gives no numbers for them.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the commercial role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.