The main difference in Option A vs Option B under NEC is quantity risk. Under Option A the Contractor prices its own lump sums and carries the risk of quantities being higher than expected. Under Option B the work is remeasured against a Bill, so the Client carries that risk and the final price moves with the quantities.

Both are priced contracts, and neither involves open-book payment. Compensation events under both use the Short Schedule of Cost Components and People Rates, and the same value engineering rule applies. The rest of this page compares them under NEC4 ECC. The main Options overview covers the other letters.

Side by side

Option AOption B
Pricing documentActivity Schedule, written by the ContractorBill of Quantities, usually written for the tenderer to price
Basis of paymentFinished activities onlyCompleted quantities at rates, plus the finished part of lump sums
Quantity riskContractorClient
Rate riskContractorContractor
Design needed at tenderEnough to price; can suit Contractor designEnough to measure
Rules for measurementNoneMethod of measurement named in the Contract Data
Mistakes in the pricing documentThe Contractor corrects them (55.1 and 55.3)The Project Manager instructs a correction, a compensation event (60.6)
Quantity differences as compensation eventsNoYes, if the tests in 60.4 or 60.5 are met
Client's final price certaintyHigher, subject to compensation eventsLower
Administrative effortLower: is the activity finished?Higher: regular measurement
Change to the pricing document in a compensation eventActivity Schedule (63.14)Bill (63.15)

Worked comparison: a fictional retaining wall

Illustrative figures. Tender drawings suggest 2,000 m³ of excavation at £40/m³, or £80,000. Actual excavation comes to 2,600 m³ because the ground profile differed from what the Contractor expected. The drawings and Scope have not changed, and the ground isn't a physical conditions event.

Option AOption B
Allowance in the tenderInside a £80,000 lump sum activity2,000 m³ at £40/m³
Paid for this work£80,0002,600 m³ at £40/m³ = £104,000
Who pays the extra £24,000ContractorClient

Under Option B, the Contractor might also have a compensation event under 60.4 if the bigger volume changes its cost per m³ and the item passes the 0.5% test. Or under 60.5 if the extra volume delays Completion.

In exchange for taking the quantity risk under Option B, the Client doesn't pay a Contractor's risk allowance on quantities. On jobs where quantities can swing widely, that can be a good deal.

Which fits your project?

SituationBetter fitWhy
Contractor designing most of the workAYou can't measure a design that doesn't exist yet
Building with a complete design and a Client wanting price certaintyAThe Contractor can take on quantity risk at a known price
Earthworks or civils where quantities are a genuine unknownBA lump sum would need a heavy risk allowance
Client team with QS measurement skills and a preference for ratesBThe Bill provides a familiar basis for valuing work
Short programme with little time to prepare a BillANo Bill to prepare

These are tendencies rather than rules. A building job with a big basement could go either way, for example. Look at how to choose an NEC main Option for other factors.

Common misconceptions

  • "Option B reprices every change at Bill rates." It doesn't. A compensation event is assessed on its effect on Defined Cost, and the result is then written into the Bill. Bill rates apply to plain measurement. See the guide to the Bill of Quantities under NEC.
  • "Option A activities are like Bill items." No: there's no part payment and no measurement. See the Activity Schedule guide.
  • "Option B payment is on cost." Not at all. Cost matters only when assessing compensation events.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.