Skip to content
Book a demo

The choice in Option A vs Option C under NEC comes down to who carries the cost overrun. Option A pays a fixed lump sum per activity, so the Contractor keeps any saving and carries any overrun. Option C pays cost plus Fee and shares the difference from a target, so both sides do.

Both use an Activity Schedule, which is why the two get confused. In Option A the schedule is what you get paid; in Option C it is only the target. This page compares them under NEC4 ECC. See the NEC main Options overview for the full list.

Side by side

Option AOption C
Monthly paymentLump sums for finished activitiesForecast Defined Cost plus the Fee
Role of the Activity ScheduleSets what is paidSets the target for the share
Cost overrunContractorShared at the share percentages
Cost savingContractorShared at the share percentages
Open book needed for paymentNoYes
Disallowed CostNot applicableApplies
Cost schedule for compensation eventsShort Schedule and People RatesFull Schedule of Cost Components
Contractor forecasts of total Defined CostNot requiredRequired at the Contract Data interval
Accepted Contractor proposal to change the Client's ScopePrices reduced by the value engineering percentage (63.12)Prices not reduced; the saving goes through the share (63.13)
Client's staffing needLowerHigher: cost review as well as progress
Contractor's cash flowLumpy, driven by finishingSmoother, following cost

The same overrun under both

A fictional project with illustrative figures. The tender is £3,000,000. There are no compensation events. The Contractor's final cost, including an equivalent Fee, is £3,300,000. Under Option C the share is a flat 50%.

Option AOption C
Client pays£3,000,000£3,150,000
Contractor's outcome against tender£300,000 worse£150,000 worse

And if the final cost is £2,800,000 instead:

Option AOption C
Client pays£3,000,000£2,900,000
Contractor's outcome against tender£200,000 better£100,000 better

In practice, the tender price itself would likely differ. A Contractor taking the whole risk under Option A generally allows more for it. That difference is hard to see at tender, but the Client pays it either way. The fuller numbers are in the Option A worked example and the Option C worked example.

How to choose

Option A is usually the better fit when:

  • the Scope is well defined and unlikely to change much;
  • the Client needs a figure it can report with confidence;
  • the Client lacks people to review Defined Cost;
  • the work is familiar and competitively priced.

Option C is usually the better fit when:

  • the work has real uncertainty, and pricing it all into a lump sum would be expensive;
  • the Contractor's ideas could change the design or the cost;
  • both sides are willing to work with open records;
  • the Client wants a Contractor involved early, including under Option X22.

For a wider set of questions, see how to choose an NEC main Option, and for how risk moves between options, see risk allocation by main Option.

Common misconceptions

  • "Option A is always cheaper for the Client." Not necessarily. The Contractor's risk allowance is in the price, and compensation events are still paid for.
  • "Option C needs a less defined Scope." It needs one good enough for a target. Too thin a Scope leads to frequent changes to the target and debates about each one.
  • "Under Option C, the Contractor can't lose money." The share of the excess is deducted from what the Contractor gets, and that can eat through its Fee.
  • "Under Option A, compensation events are the same as under Option C." Both assess on forecast effects, but different schedules apply. In Option A, the result changes payment. In Option C, it changes only the target. For more, read about events under Option A and events under Option C.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Take the NEC4 ECC quiz, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.