ECC vs PSC: Works or Professional Services?

Use the ECC to buy construction work and the NEC PSC (Professional Service Contract) to buy expertise, such as design, surveys and advice. The clearest test is the deliverable: if you are paying for something built, it's the ECC; if you are paying for skilled people's time and judgement, it's the PSC.

The two forms share many clause numbers, but they place different duties on the provider. Each has its own guide, the NEC4 ECC and the NEC4 PSC, and the full list is under NEC contract types.

Comparison table

TopicNEC4 ECCNEC4 PSC
PartiesClient and ContractorClient and Consultant
AdministratorProject Manager and SupervisorService Manager
What is providedThe worksThe service
Main OptionsA, B, C, D, E, FA, C, E
Site, Equipment, Plant and MaterialsYesNo
Tests, inspections, searchesYesNo
DefectsNotified at 43.2 and correctedNotified at 41.1 and corrected at 41.2, with no defect correction period
Uncorrected Defect46.141.2
Illegal or impossible requirement17.216.2
Prevention19.1 and 60.1(19)18.1 and 60.1(12)
Compensation events21, including weather and physical conditions16, with neither of those
Corrected Client informationNo equivalent core event60.1(14), with 14.3
Consultant's or Contractor's Defect not its faultDealt with through Option X15Core event 60.1(13)

Numbers that match include early warning (15.1 to 15.4), programme (31.1 to 32.2), payment (50.1, 50.2, 50.5, 51.1 to 51.3), the final assessment (53.1 to 53.3) and the compensation event procedure in 61 to 66.

The difference that matters most

A PSC Consultant generally owes reasonable professional skill and care. A Contractor under the ECC has to provide works that meet the Scope, including any design it has taken on. So a design that turns out to be wrong without negligence could be the Contractor's problem under the ECC, but not the Consultant's under the PSC.

The X15 Option in the ECC exists to limit a Contractor's design liability to a similar standard. Insurance is the other half of this. Professional indemnity cover is usually written around negligence, so a tighter duty can leave a gap.

Grey areas

The jobUsuallyWhy
Design only, others buildPSCNo physical work
Design and build by one firmECCThe result is works. The designer's own appointment may be a PSS
Site investigation with drilling, plus a reportEither. Depends on which is the main partHeavy intrusive work suits the ECC, including its physical conditions event. A small investigation can go on the PSC
Project management or supervisionPSCA service, even though it happens on site
Early contractor input before constructionECC with an involvement Option, or a separate PSCSee early contractor involvement
A short, simple surveyPSSCNo need for a Service Manager

Why using the wrong form hurts

A Client that puts a designer on the ECC may be surprised by the price, since the provider's insurer may not cover that level of liability. The clauses on Equipment, Plant and Materials and tests would also have little to apply to. On the other hand, a contractor doing physical work on a PSC has no compensation events for ground conditions or weather, and no structure for testing, take over or Defects Certificates. Either way, you end up writing Z clauses to fix a problem the right form would have avoided.

Payment thinking is different too

Under the ECC, a big part of the cost is plant, materials and subcontractors. In a professional appointment the main cost is people's time, so rates, hours and the fee matter most. The guide to professional services under NEC explains how this works. The PSC Options are named differently too: there is no Option B or D, and the NEC3 PSC's term Option G was not carried into NEC4.

Three questions to decide

  1. At the end, what does the Client receive: something built, or information and advice?
  2. Does the provider need the works risks and procedures (weather, ground, tests, take over)?
  3. What standard should the provider be held to, and does its insurance respond to that standard?

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Test your NEC knowledge, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.