Skip to content
Book a demo

NEC Contract Types: Which Form Do You Need?

The NEC contract types are a family of forms that share one approach but differ by what you are buying: construction work, professional services, ongoing services, goods, or a combination. To pick the right one, ask what is being bought, how complex and risky it is, and whether you are the main contractor or letting work below one.

This guide covers the NEC4 suite, first published in June 2017 and since amended. NEC3 equivalents exist for many forms and are noted where they matter. For the wider background, start with the complete guide to NEC contracts. If you want a decision route rather than an overview, go straight to how to choose the right NEC contract.

The forms at a glance

You are buyingFull formSubcontractShort form
Construction and engineering workECCECSECSC (short subcontract: ECSS)
Professional servicesPSCPSSPSSC
A service over a period, such as maintenanceTSCTSSTSSC
Facilities managementFMCFacilities Management SubcontractFacilities Management Short Contract
Goods and related servicesSCNone in the suiteSSC
Design, construction and operation from one providerDBONot applicableNot applicable
A multi-party alliance on a major project or programmeALCNot applicableNot applicable
A set of suppliers on call for a termFCNot applicableNot applicable
An adjudicator or dispute board memberDRSCNot applicableNot applicable

Who does what in each form

Names change more than people expect, and using the wrong ones in letters causes confusion. The short forms have no contract administrator: the paying party gives the instructions and makes the assessments itself.

FormPaying partyProviding partyAdministratorMain Options
ECCClientContractorProject Manager and SupervisorA, B, C, D, E, F
ECSContractorSubcontractorContractorA, B, C, D, E
ECSCClientContractorNoneNone
ECSSContractorSubcontractorNoneNone
PSCClientConsultantService ManagerA, C, E
PSSContractorSubcontractorContractorA, C, E
PSSCClientConsultantNoneNone
TSCClientContractorService ManagerA, C, E
TSSContractorSubcontractorContractorA, C, E
TSSCClientContractorNoneNone
SCPurchaserSupplierSupply ManagerNone: one priced form
SSCPurchaserSupplierNoneNone

The full explanation of the letters is in the guide to the NEC main Options, with separate pages on the PSC Options and the TSC Options. Remember that the Options are not the same across forms: Option E in the ECC and Option E in a service contract share an idea, not their wording.

Construction and engineering forms

Most NEC users work on one of these four.

Two comparison pages help at the boundary. ECC vs ECSC covers whether a job justifies the full form, and back-to-back NEC subcontracts shows how periods line up through a chain, and where they deliberately do not.

Professional service forms

These appoint designers, advisers, project managers and other consultants. The standard is skill and care rather than an outcome, and there is no Site, Equipment or Plant and Materials in the sense the works contracts use.

Term service and facilities management forms

These cover work over a period of time, not a single project with one end date. Time is managed task by task, not against one Completion Date.

Supply forms

The vocabulary shifts here to Purchaser, Supplier and Delivery. The NEC4 Supply Contract is for high-value goods and related services, with a Supply Manager. The Supply Short Contract is for lower-risk purchases under one order or by Batch Order, and the Purchaser administers it directly.

Integrated, multi-party and appointment forms

What stays the same, and what doesn't

The shared DNA is why moving between forms feels familiar. Across the main forms, you will find a duty of mutual trust and co-operation, early warning at clause 15, the programme or plan at clause 31, payment at clause 50, and compensation events at clause 60. Learning one form gives you a head start on the rest.

The trap is assuming the detail carries across. Some examples:

TopicHow it varies between NEC4 forms
Compensation events21 in the ECC, 18 in the TSC and SC, 16 in the PSC, 12 in the ECSC and ECSS, 9 in the SSC and 8 in the PSSC, each with its own numbering. So 60.1(12) means physical conditions in the ECC, but something else in the others.
Early warningA register and meetings in the full forms; a duty to warn and co-operate, with no register or formal meetings, in the short forms.
ProgrammeAccepted Programme in the ECC, PSC and SC; a plan plus Task Order programmes in the TSC; programmes supplied as the Scope says in the short forms.
Time bar for notifying a compensation eventEight weeks in the ECC, seven in the ECS and PSS. Read the figure in the form you are actually using.
Construction Act wordingOption Y(UK)2 in the ECC, PSC and TSC; numbered conditions in short forms such as the PSSC; not an Option in the SC at all.

Copying a clause reference from one form into a letter under another is an easy way to send an invalid-looking notice. Keep the right form open when you write.

Mistakes people make when choosing

  • Choosing by contract value alone. Nothing in the short forms sets a financial limit. The test is whether the work is straightforward and low risk, and a small job with difficult ground or several interfaces may still need the ECC.
  • Using a works contract for a service, or the reverse. A five-year maintenance arrangement forced onto the ECC leaves you without Task Orders. A design commission on the ECC brings in a level of liability the designer may not have intended.
  • Mixing subcontract forms casually. The ECS is designed for use under an NEC4 main contract. Before using it elsewhere, look at what depends on the main contract, such as the joining of adjudications and termination links.
  • Treating a framework as a contract for the work. The framework sets how orders are placed. The obligations to deliver and pay sit in each order's own contract.
  • Not budgeting for administration. Full forms assume someone is available to reply on time. If nobody will do that, choosing the ECC does not produce the benefits, and late replies themselves become compensation events.

Editions

A contract keeps the edition it was signed under, so plenty of NEC3 work is still running. Names and numbers changed between the editions: the Employer became the Client and Works Information became the Scope. The differences are in NEC3 vs NEC4. Also confirm which amendments your copy includes, since NEC has reissued the NEC4 forms with changes since 2017.

All guides in this section

Free NEC tools, quizzes and downloads

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Test your NEC knowledge, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.