NEC4 ECC: who does what, by when
The main clocks on an unamended NEC4 Engineering and Construction Contract, sorted by whose job it is. Using another form? See time periods by contract, because the subcontract and short forms differ.
Contractor
| Step | Clause | Time | The clock starts at |
|---|---|---|---|
| Notify a compensation event (the time bar) | 61.3 | 8 weeks | Date you became aware that the event has happened |
| Submit a quotation | 62.3 | 3 weeks | Date of the instruction to quote |
| Submit a revised quotation | 62.4 | 3 weeks | Date of the instruction to revise |
| First programme, where none is named in the Contract Data | 31.1 | As stated in the Contract Data | Contract Date |
| Revised programme when instructed | 32.2 | As stated in the Contract Data | Date of the instruction |
| Next regular revised programme | 32.2 | As stated in the Contract Data | Date of the last revised programme |
| Correct a notified Defect | 44.2 | As stated in the Contract Data | The date the period starts: see the note |
Project Manager
| Step | Clause | Time | The clock starts at |
|---|---|---|---|
| Reply to a notified compensation event | 61.4 | 1 week | Date the Contractor notified the event |
| No reply to a notified event: treated as accepted | 61.4 | 2 weeks | Date the Contractor notified the failure to reply |
| Reply to a quotation | 62.3 | 2 weeks | Date the quotation was submitted |
| No reply to a quotation: treated as accepted | 62.6 | 2 weeks | Date the Contractor notified the failure to reply |
| Notify your own assessment | 64.3 | 3 weeks | Date it became clear your own assessment was needed |
| No reply on an assessment: treated as accepted | 64.4 | 2 weeks | Date the Contractor notified the failure |
| Reply to a programme submitted for acceptance | 31.3 | 2 weeks | Date the programme was submitted |
| No reply to a programme: treated as accepted | 31.3 | 1 week | Date the Contractor notified the failure to reply |
| First Early Warning Register | 15.2 | 1 week | Starting date |
| First early warning meeting | 15.2 | 2 weeks | Starting date |
| Revised register after an early warning meeting | 15.4 | 1 week | Date of the meeting |
| Certify a payment | 51.1 | 1 week | Assessment date |
| Certify Completion | 30.2 | 1 week | Date of Completion |
| Final assessment after the Defects Certificate | 53.1 | 4 weeks | Date of the Defects Certificate |
| Final assessment after a termination certificate | 53.1 | 13 weeks | Date of the termination certificate |
Project Manager or Contractor
| Step | Clause | Time | The clock starts at |
|---|---|---|---|
| Any other reply (the period for reply) | 13.3 | As stated in the Contract Data | Date the communication was received |
The paying Party
| Step | Clause | Time | The clock starts at |
|---|---|---|---|
| Make the certified payment | 51.2 | 3 weeks | Assessment date |
| Pay less notice (Option Y(UK)2) | Y2.3 | 7 days before | Final date for payment |
The steps marked "treated as accepted" only start once the Contractor has notified the failure to reply. Read time bars for what happens if a date is missed.
Where next?
Work out a real date in the deadline calculator, look up any clause in the clause finder, or test yourself with a quiz.
General information in our own words, not legal advice. Your own contract, its Contract Data and any Z clauses decide.