NEC4 ECC: who does what, by when

The main clocks on an unamended NEC4 Engineering and Construction Contract, sorted by whose job it is. Using another form? See time periods by contract, because the subcontract and short forms differ.

Contractor

StepClauseTimeThe clock starts at
Notify a compensation event (the time bar)61.38 weeksDate you became aware that the event has happened
Submit a quotation62.33 weeksDate of the instruction to quote
Submit a revised quotation62.43 weeksDate of the instruction to revise
First programme, where none is named in the Contract Data31.1As stated in the Contract DataContract Date
Revised programme when instructed32.2As stated in the Contract DataDate of the instruction
Next regular revised programme32.2As stated in the Contract DataDate of the last revised programme
Correct a notified Defect44.2As stated in the Contract DataThe date the period starts: see the note

Project Manager

StepClauseTimeThe clock starts at
Reply to a notified compensation event61.41 weekDate the Contractor notified the event
No reply to a notified event: treated as accepted61.42 weeksDate the Contractor notified the failure to reply
Reply to a quotation62.32 weeksDate the quotation was submitted
No reply to a quotation: treated as accepted62.62 weeksDate the Contractor notified the failure to reply
Notify your own assessment64.33 weeksDate it became clear your own assessment was needed
No reply on an assessment: treated as accepted64.42 weeksDate the Contractor notified the failure
Reply to a programme submitted for acceptance31.32 weeksDate the programme was submitted
No reply to a programme: treated as accepted31.31 weekDate the Contractor notified the failure to reply
First Early Warning Register15.21 weekStarting date
First early warning meeting15.22 weeksStarting date
Revised register after an early warning meeting15.41 weekDate of the meeting
Certify a payment51.11 weekAssessment date
Certify Completion30.21 weekDate of Completion
Final assessment after the Defects Certificate53.14 weeksDate of the Defects Certificate
Final assessment after a termination certificate53.113 weeksDate of the termination certificate

Project Manager or Contractor

StepClauseTimeThe clock starts at
Any other reply (the period for reply)13.3As stated in the Contract DataDate the communication was received

The paying Party

StepClauseTimeThe clock starts at
Make the certified payment51.23 weeksAssessment date
Pay less notice (Option Y(UK)2)Y2.37 days beforeFinal date for payment

The steps marked "treated as accepted" only start once the Contractor has notified the failure to reply. Read time bars for what happens if a date is missed.