The NEC task definition belongs mainly to the term service forms: a Task is a piece of work within the service that the Service Manager calls off through a Task Order. It isn't the Engineering and Construction Contract's term, so if you're on an ECC, you won't find it in your core clauses.

Where it applies, the term sets the boundary between what the Contractor does as a matter of course and what it does only when asked. This page explains the term in the NEC4 Term Service Contract (TSC). Check the numbers and rules against your own contract. For the instruction itself, see Task Orders explained. This page is part of the NEC definitions glossary.

Three linked terms

TermWhat it isExample on a highways term contract
The serviceThe whole of what the contract provides forMaintain the network's drainage and surfacing for five years
TaskA specific piece of work within the serviceReline 200m of culvert under the A-road at a given location
Task OrderThe Service Manager's instruction to carry out a TaskThe numbered order that gives the description, dates and price

The word "within" is doing a lot. A Task that falls outside the service isn't properly a Task, however the order is headed.

Where it appears by form and edition

FormHow Tasks work
NEC4 TSCTask Orders are in core clause 19
NEC3 TSCAdded through Option X19, a different meaning from X19 in NEC4 TSC. See the X19 guide
NEC3 Professional Service ContractOption G, in which the Employer instructs Tasks from a Task Schedule
NEC4 ECCNo Task or Task Order in the core clauses

A worked example

A fictional water company term contract, with illustrative figures, using the NEC4 TSC.

  1. The Service Manager wants a 150mm valve replaced at a pumping site. It's within the service.
  2. The Price List has a rate of £2,400 for this item, so a Task Order issues at that price. It describes the work, states a starting date and gives a Task Completion Date.
  3. On arrival, the Contractor finds the valve is a different size, buried under a new slab. The Service Manager instructs a change to the Task. That's a compensation event under 60.1(1) in the TSC.
  4. Separately, the order reaches the Contractor two days after its stated start. The TSC lists that as its own compensation event at 60.1(4), which isn't the same as 60.1(4) in the ECC.

Delay on that Task is measured against the Task Completion Date (63.6 in the TSC set) instead of a date for the whole contract.

Why it causes problems

  • Thin descriptions. "Repair drainage, Site 4" reads fine on the day. Two years on, nobody can tell whether a late extra was inside the Task. Give location, extent and any exclusions.
  • Work done without an order. When a crew attends an emergency and paperwork follows, the Task arguably doesn't exist yet, and neither does the price. Decide how urgent work will be authorised when you start, and keep to it.
  • Using Tasks for everything. Routine services are often better priced as a recurring item. If each small job needs an order, the admin can cost more than the work.
  • Quoting ECC numbers. The compensation event numbers in the TSC differ from the ECC list. For example, 60.1(4) isn't the same event, so always say which form you're citing.
  • Tasks running past the end of the term. Check what your contract says about orders late in the term, particularly on a long framework.

The Term Service Contract guide explains how Tasks fit with the Price List and the plan.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Search the NEC glossary, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.