Skip to content
Book a demo

The NEC subcontractor definition is narrower than everyday usage. A Subcontractor is someone with a contract with the Contractor to do certain kinds of work on the job. Not everyone the Contractor pays qualifies: most suppliers don't, and whether plant hire or agency labour does can depend on the edition.

This matters because the classification affects who has to be accepted, how costs are recovered and who counts as Others. The NEC3 ECC definition is at 11.2(17). For NEC4, this page follows the equivalent definition in the NEC4 subcontract, where the term is Subsubcontractor, so check the wording in your own NEC4 ECC. This page is part of the NEC definitions glossary.

What the two editions look at

NEC3 ECCNEC4 (from the subcontract wording)
Build or install part of the worksYesYes
DesignNot in itself, unless it amounts to a service necessary to Provide the WorksYes: design of all or part of the works, except a supplier's design of its own Plant and Materials
ServicesA service necessary to Provide the WorksA service in the Working Areas necessary to Provide the Works
Bespoke supplyYes, where the supplier designs the Plant and Materials, in whole or part, specifically for this jobNot by that route
ExclusionsNone stated in that listHire of Equipment; people paid for according to the time they work

Test cases

CompanyNEC3NEC4 (subcontract wording)
Groundworks firm doing part of the worksSubcontractorSubcontractor
Readymix supplier delivering standard concreteNot a SubcontractorNot a Subcontractor
Manufacturer designing a bespoke switchboard, then supplying itSubcontractorNot by that route
Design consultant engaged by the ContractorLikely, as a serviceSubcontractor
Hired excavator with no operatorDepends on the serviceExcluded
Labour agency paid by the hourDepends on the serviceExcluded

Read both columns as a guide for thinking, not a final answer. The facts matter, as does any Z clause.

Where it matters

  • Acceptance. Each proposed Subcontractor's name goes to the Project Manager for acceptance, along with the proposed subcontract conditions unless they're an NEC form or have already been accepted (clause 26). Appointing without that is a breach, and it can have cost effects on Options C, D and E.
  • Responsibility. The Contractor stays responsible for the work as if it hadn't subcontracted (26.1).
  • Payment. On cost-based Options, amounts paid to Subcontractors feed Defined Cost by a different route from the Contractor's own costs. See subcontractor costs.
  • Fee. In NEC3, the subcontracted fee percentage applies to the Defined Cost of subcontracted work, so a wrong label changes the money.
  • Others. A Subcontractor can't be one of Others, so its delays don't give rise to a 60.1(5) event.

A worked example

A fictional NEC3 Option C job, with illustrative rates. A steel firm is engaged to design and fabricate a bespoke staircase, then install it. Direct fee is 12%, and subcontracted fee 4%.

The firm clearly installs part of the works, so it's a Subcontractor. The Contractor should have submitted its name and conditions. Its £200,000 cost is at the subcontracted rate, which gives £8,000 of Fee. Had the Contractor recorded it as a supplier, the direct rate could have produced £24,000, an overclaim of £16,000 that an audit would be likely to catch. The label has real consequences.

What people get wrong

  • Using "subcontractor" for all supply chain firms. In correspondence, use the defined term only when it applies.
  • Thinking it reaches every tier. The definition covers those with a contract with the Contractor. Lower tiers aren't Subcontractors under the main contract, and they don't get a direct route to the Client.
  • Forgetting the NEC4 wording moved the test. A firm treated as a Subcontractor on an NEC3 job may not be one on the next NEC4 job.
  • Assuming back-to-back terms apply themselves. The subcontract needs its own terms. The guide to managing subcontracts covers how to keep these in step.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Search the NEC glossary, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.