For NEC vs GC/Works, the practical answer is that NEC is the current choice and GC/Works is mainly a legacy form. GC/Works contracts were drafted for government work and are still available, but they are no longer being updated. Government guidance has instead pointed public clients towards NEC and other standard forms.

You may still meet GC/Works when you are managing an older contract, dealing with a final account or working with a client that keeps the form for its own reasons. This page gives general differences only, and GC/Works has several variants and many amended versions, so read the actual conditions. For other forms, see the NEC comparisons overview.

What GC/Works is

GC/Works is a family of government conditions of contract for building and civil engineering. The best known is GC/Works/1, with other versions covering smaller works, mechanical and electrical work and related uses. They were long associated with central government and defence estates.

The forms were written from the government client's point of view. They are generally seen as giving the client's representative strong powers, which suited a public body running its own projects at the time.

Side by side

TopicNEC4 ECCGC/Works (general)
StatusCurrent edition published in 2017, with later amendmentsAvailable but not being updated by government
Who administersProject Manager and Supervisor, with separate dutiesProject Manager and Quantity Surveyor roles are typically central
Pricing routesPriced, target, cost reimbursable or management in one familyConventional routes, with versions for different job types
Change and delayCompensation events deal with both together, using a quotationUsually separate treatment, under the terms of the version used
Risk sharingEarly warnings for both sides, plus defined Client's liabilitiesGenerally thought of as more client-favourable
Modern OptionsInformation modelling (X10), multiparty collaboration (X12), KPIs (X20), project bank account (Y(UK)1)Added by amendment, where at all
StyleProcedures with clear time limits on both sidesA more traditional drafting style in which the client's representative decides

The change in mindset

The largest change isn't in the paperwork. Under a client-led form, a contractor's team may be used to waiting for decisions and then making its case. Under NEC, both sides are working to deadlines, and the client side can create a compensation event just by being late: 60.1(6) makes a late reply an event in its own right.

For public bodies, this has a practical consequence. Internal approvals that used to take as long as they took may now need delegated limits, so a Project Manager can respond in time. Our guide to tracking the period for reply covers this in more detail.

Moving a team from GC/Works to NEC

  1. Confirm which contract you are on. A framework may have moved to NEC while older call-offs stay on GC/Works. Run each under its own terms, even when they're on the same site.
  2. Don't convert a running contract by habit. A live GC/Works job doesn't pick up NEC procedures unless the contract is formally changed.
  3. Train client staff as well as contractors. Project Managers and anyone whose sign-off affects a reply need to know the time limits.
  4. Review your templates. Old notice letters and forms won't use NEC terms or refer to the right procedures. See NEC letter templates.
  5. Rethink what you amend. Taking old GC/Works provisions and adding them as Z clauses can create conflicts with the NEC mechanisms. Keep any Z clauses specific and test them against the core clauses.
  6. Set up records from the start. NEC assessments rely on Defined Cost and an up-to-date programme.

If you are still running a GC/Works contract

The form's age doesn't make the contract any less binding. Follow its notice provisions, keep your records and take legal advice on any dispute, as case law and guidance written for NEC won't necessarily help. If you are procuring something new, check current government policy and your framework's requirements, starting with who has to use NEC.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.