JCT and NEC often describe similar ideas in different words, so this table gives the closest NEC term for each familiar JCT phrase. Treat it as a way in, not an exact translation: several NEC terms work differently from the JCT term beside them, and those differences are where people get caught.
NEC terms here are from the NEC4 ECC, with NEC3 names noted. JCT terms differ across forms and editions. For the bigger picture, read JCT vs NEC: the main differences or return to the NEC comparisons overview.
People and documents
| JCT term | Closest NEC4 ECC term | How it differs |
|---|---|---|
| Employer | Client (NEC3: Employer) | Same party, new name in NEC4 |
| Architect / Contract Administrator | Project Manager | The Project Manager acts for the Client and isn't framed as an independent certifier in the JCT way |
| Employer's Agent | Project Manager | A loose match; the NEC role has its own duties and time limits |
| Clerk of Works | Supervisor | The Supervisor has defined contractual powers over tests and Defects |
| Contract Particulars | Contract Data | In two parts, one from the Client and one from the Contractor |
| Employer's Requirements; specification and drawings | Scope (NEC3: Works Information) | A single defined term for what is to be provided and any constraints on how |
| Contractor's Proposals | Part of the Scope; Contractor's design goes through acceptance (21) | No separate standard label |
| Contract Bills | Bill of Quantities (Options B and D only) | Options A and C use an Activity Schedule instead |
| Contract Sum | Total of the Prices | What "Prices" means depends on the main Option |
| Base Date | No direct equal; the Contract Date is the nearest reference point | Not the same test, so check what your contract uses it for |
Time
| JCT term | Closest NEC4 ECC term | How it differs |
|---|---|---|
| Date for Completion | Completion Date | Moves mainly through implemented compensation events or agreed acceleration |
| Practical Completion | Completion | NEC defines it, relying heavily on what the Scope requires by the date; don't read JCT practice across |
| Master programme | Accepted Programme | Far more content is required, and it sets the baseline for assessing delay |
| Relevant Event / extension of time | Compensation event changing the Completion Date | Assessed from its effect on planned Completion, so the delay may not equal the days lost on one activity (63.5) |
| Sections and Sectional Completion | Option X5 | Secondary Option, included only if chosen |
| Partial possession | Take over (35), and possibly 60.1(15) | Taking over part early can be a compensation event |
| Liquidated damages | Delay damages, Option X7 | Apply only if X7 is chosen |
| Non-Completion Certificate | No equivalent | X7 doesn't rely on this kind of certificate |
Money and change
| JCT term | Closest NEC4 ECC term | How it differs |
|---|---|---|
| Variation | Change to the Scope, 60.1(1) | Assessed as a compensation event on Defined Cost plus Fee, not by default on contract rates |
| Loss and expense / Relevant Matter | Compensation event | Handled in one assessment with the time effect |
| Interim Certificate / valuation | Payment certificate (51.1), following an assessment (50.1) | The Project Manager assesses it, and it is based on the Price for Work Done to Date |
| Final Certificate / final account | Final assessment (53) | New in NEC4 and tied to the Defects Certificate or a termination |
| Pay Less Notice | Pay less notice, Option Y(UK)2 | Construction Act concept in both |
| Fluctuations | Option X1 | Index-based, and available only with the main Options that allow it |
| Retention | Option X16 | Applies only if chosen |
| Provisional sum | No standard equivalent | Often handled through the Scope, a later compensation event or an amendment |
| Dayworks | No direct equivalent | Assessment uses Defined Cost; the Schedule of Cost Components sets out what counts |
Quality, security and disputes
| JCT term | Closest NEC4 ECC term | How it differs |
|---|---|---|
| Rectification Period | Defects date and defect correction periods | Two separate ideas: when the hunt for Defects ends, and how long each correction may take (44.2) |
| Certificate of Making Good | Defects Certificate | Issued at the defects date, or later if notified Defects remain, and can list outstanding Defects |
| Performance bond | Option X13 | Secondary Option |
| Parent company guarantee | Option X4 | NEC4 refers to the ultimate holding company |
| Collateral warranties / third party rights | X8 undertakings, Y(UK)3 | Check exactly what has been selected |
| Contractor's Designed Portion | Contractor's design set by the Scope; X15 covers liability | No separate standard "portion" concept |
| Adjudication and arbitration or litigation | Dispute resolution Option W2 under the Construction Act; W1 where it doesn't apply | Only one W option is chosen, and the final tribunal is named in the Contract Data |
| Determination | Termination (90 to 93) | Uses a table of reasons, procedures and payment |
Four words that catch out JCT users
- "Accept". Accepting a programme or design doesn't take away the Contractor's responsibility. The Project Manager's response has its own rules and permitted reasons for refusal.
- "Others". This is a defined term for people outside the contract, not a general word.
- "Defect". It is measured against the Scope and the applicable law, not against a general idea of poor work.
- "Notify". Many NEC communications must be separate notifications. A mention in the minutes may not be enough, and clause 13 is worth reading early.
Related guides
- NEC vs Other Construction Contracts
- NEC vs FIDIC
- NEC vs ICC
- NEC vs GC/Works
- JCT vs NEC: The Main Differences
- Difference Between JCT and NEC for Clients
See how this works in practice
Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.
Take the guided tour Book a demo
Use the contract picker, use the free NEC tools or download free NEC templates.
This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.