JCT and NEC often describe similar ideas in different words, so this table gives the closest NEC term for each familiar JCT phrase. Treat it as a way in, not an exact translation: several NEC terms work differently from the JCT term beside them, and those differences are where people get caught.

NEC terms here are from the NEC4 ECC, with NEC3 names noted. JCT terms differ across forms and editions. For the bigger picture, read JCT vs NEC: the main differences or return to the NEC comparisons overview.

People and documents

JCT termClosest NEC4 ECC termHow it differs
EmployerClient (NEC3: Employer)Same party, new name in NEC4
Architect / Contract AdministratorProject ManagerThe Project Manager acts for the Client and isn't framed as an independent certifier in the JCT way
Employer's AgentProject ManagerA loose match; the NEC role has its own duties and time limits
Clerk of WorksSupervisorThe Supervisor has defined contractual powers over tests and Defects
Contract ParticularsContract DataIn two parts, one from the Client and one from the Contractor
Employer's Requirements; specification and drawingsScope (NEC3: Works Information)A single defined term for what is to be provided and any constraints on how
Contractor's ProposalsPart of the Scope; Contractor's design goes through acceptance (21)No separate standard label
Contract BillsBill of Quantities (Options B and D only)Options A and C use an Activity Schedule instead
Contract SumTotal of the PricesWhat "Prices" means depends on the main Option
Base DateNo direct equal; the Contract Date is the nearest reference pointNot the same test, so check what your contract uses it for

Time

JCT termClosest NEC4 ECC termHow it differs
Date for CompletionCompletion DateMoves mainly through implemented compensation events or agreed acceleration
Practical CompletionCompletionNEC defines it, relying heavily on what the Scope requires by the date; don't read JCT practice across
Master programmeAccepted ProgrammeFar more content is required, and it sets the baseline for assessing delay
Relevant Event / extension of timeCompensation event changing the Completion DateAssessed from its effect on planned Completion, so the delay may not equal the days lost on one activity (63.5)
Sections and Sectional CompletionOption X5Secondary Option, included only if chosen
Partial possessionTake over (35), and possibly 60.1(15)Taking over part early can be a compensation event
Liquidated damagesDelay damages, Option X7Apply only if X7 is chosen
Non-Completion CertificateNo equivalentX7 doesn't rely on this kind of certificate

Money and change

JCT termClosest NEC4 ECC termHow it differs
VariationChange to the Scope, 60.1(1)Assessed as a compensation event on Defined Cost plus Fee, not by default on contract rates
Loss and expense / Relevant MatterCompensation eventHandled in one assessment with the time effect
Interim Certificate / valuationPayment certificate (51.1), following an assessment (50.1)The Project Manager assesses it, and it is based on the Price for Work Done to Date
Final Certificate / final accountFinal assessment (53)New in NEC4 and tied to the Defects Certificate or a termination
Pay Less NoticePay less notice, Option Y(UK)2Construction Act concept in both
FluctuationsOption X1Index-based, and available only with the main Options that allow it
RetentionOption X16Applies only if chosen
Provisional sumNo standard equivalentOften handled through the Scope, a later compensation event or an amendment
DayworksNo direct equivalentAssessment uses Defined Cost; the Schedule of Cost Components sets out what counts

Quality, security and disputes

JCT termClosest NEC4 ECC termHow it differs
Rectification PeriodDefects date and defect correction periodsTwo separate ideas: when the hunt for Defects ends, and how long each correction may take (44.2)
Certificate of Making GoodDefects CertificateIssued at the defects date, or later if notified Defects remain, and can list outstanding Defects
Performance bondOption X13Secondary Option
Parent company guaranteeOption X4NEC4 refers to the ultimate holding company
Collateral warranties / third party rightsX8 undertakings, Y(UK)3Check exactly what has been selected
Contractor's Designed PortionContractor's design set by the Scope; X15 covers liabilityNo separate standard "portion" concept
Adjudication and arbitration or litigationDispute resolution Option W2 under the Construction Act; W1 where it doesn't applyOnly one W option is chosen, and the final tribunal is named in the Contract Data
DeterminationTermination (90 to 93)Uses a table of reasons, procedures and payment

Four words that catch out JCT users

  • "Accept". Accepting a programme or design doesn't take away the Contractor's responsibility. The Project Manager's response has its own rules and permitted reasons for refusal.
  • "Others". This is a defined term for people outside the contract, not a general word.
  • "Defect". It is measured against the Scope and the applicable law, not against a general idea of poor work.
  • "Notify". Many NEC communications must be separate notifications. A mention in the minutes may not be enough, and clause 13 is worth reading early.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the contract picker, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.