NEC originally stood for New Engineering Contract. That's the answer to what does NEC contract stand for, but today NEC works as a name in its own right, because the family now goes well beyond engineering and the first edition is more than 30 years old.

In construction, then, "NEC" means this family of standard contracts, owned by the Institution of Civil Engineers. To learn more, read what an NEC contract is or the comparisons section.

How the name developed

WhenWhat happened
1991A consultative edition appears
1993The first edition is published
1995The second edition follows, and the main works form takes the title Engineering and Construction Contract
2005The third edition, NEC3, is published, with reprints with amendments up to April 2013
2017The fourth edition, NEC4, is published in June

The full story is in the history of NEC.

Other things NEC might mean

If you've found this page while searching for something else, NEC may mean a different thing altogether. In the US, it often refers to the National Electrical Code, while in electronics it's the Japanese company NEC Corporation. Neither has any connection with these contracts. On a UK construction site or in a tender, assume the contract unless the context says otherwise.

Abbreviations you'll meet alongside NEC

These all come up regularly, and the same terms apply to both editions unless noted.

AbbreviationStands forUsed for
ECCEngineering and Construction ContractMain works contract
ECSEngineering and Construction SubcontractSubcontracted works
ECSCEngineering and Construction Short ContractSimpler works
ECSSEngineering and Construction Short SubcontractSimpler subcontracted works
PSCProfessional Service ContractConsultants and designers
PSSCProfessional Service Short ContractSimpler appointments
TSCTerm Service ContractMaintenance and services over a period
TSSCTerm Service Short ContractSimpler term services
CECompensation eventAn event that may change the Prices and dates
EWEarly warningA notified risk to time, cost or performance
PMProject ManagerManages the contract for the Client
SCCSchedule of Cost ComponentsWhat counts towards Defined Cost
PWDDPrice for Work Done to DateThe basis of each payment
TRATime risk allowanceTime allowed in the programme for risks

A common slip

People often say "the NEC" and "NEC4" as though they were interchangeable, or quote a clause from memory without the edition. That can cause real confusion, because early warnings are clause 15 in the NEC4 ECC but clause 16 in the NEC3 ECC. When you write a letter or minute, give the form and edition, such as "NEC4 ECC clause 15.1". It takes a few extra seconds and prevents misunderstandings, especially when the letter may be read years later by someone who was never on the job.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the contract picker, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.