Skip to content
Book a demo

Keeping a Defects Register

An NEC defects register is a working log of every Defect: when it was notified, when its correction period started, when it is due, and how it was closed. The contract doesn't require one by name, but without it you can't reliably run the correction process or produce an accurate Defects Certificate.

It supports the NEC quality and Defects process, where many end-of-job arguments come down to dates. A register that records those dates properly settles many of them before they start.

The fields worth keeping

FieldWhy it matters
ReferenceA unique number used in every related letter
LocationGrid, level, chainage or room, so anyone can find it
DescriptionFactual and short
Scope or design referenceWhat it departs from. This is what makes it a Defect
SourceInspection, test, search or a report from the occupier
Notified by, and dateSupervisor or Contractor, under NEC4 43.2 or NEC3 42.2
Date Completion certifiedSets the start of the period for earlier notifications
Period start dateCompletion, notification, or access to a taken-over part
Length of periodFrom the Contract Data, including any special periods
Correct byStart date plus the period
Access: requested and givenDecides which uncorrected Defect rule applies
Action ownerOften a subcontractor
Closure routeCorrected, accepted by quotation, or uncorrected and assessed
Closure date and evidenceInspection record, repeat test or photographs

A sample entry

Fictional, with illustrative dates and a 4-week period.

FieldEntry
ReferenceDN-031
LocationBlock B, Level 2, plant room door D2-14
DescriptionFire door gap exceeds the tolerance in the specification
NotifiedBy Supervisor, 12 May
Completion30 June
Period starts30 June (notified before Completion)
Correct by28 July
Closed19 July, corrected, re-inspected by Supervisor

Note that the due date is 28 July, not 9 June. A register that automatically adds the period to the notification date would show this item as overdue for weeks, when it wasn't. The guide to correcting Defects sets out the rule.

How to run it

  1. Keep one register. Separate Supervisor and Contractor lists diverge within weeks. Share a single version.
  2. Enter every notification straight away. That includes Defects the Contractor finds itself.
  3. Review it at a regular meeting. Focus on items due in the next two periods, and on items waiting for access.
  4. Recalculate at Completion. All open Defects notified earlier get their start date on that day. Check them as a batch.
  5. Close items only with evidence. A Contractor's statement that something's been fixed isn't enough on its own.
  6. Reconcile before the certificate. The Defects Certificate should be derived from this list.

Reports worth pulling

  • Open Defects by subcontractor or work package.
  • Items overdue, and items due in the next fortnight.
  • Defects stuck for lack of access, with the date first requested.
  • Defects by trade, as an early sign of a wider quality problem. A pattern may justify a search elsewhere, or a look at the quality plan.

What goes wrong

  • Mixing snags and Defects. If you keep both in one list, add a column to say which is which. Only Defects run on the contract's clock.
  • No link to the Scope. Without a reference to the requirement, a later reader can't tell if it was a Defect at all.
  • A spreadsheet with no history. If someone overwrites a date, nobody can see what was there before. Keep the original notices, and lock or log changes. Contract Status records Defects and their dates against the contract, but a well-kept controlled sheet will do the same job on a smaller scheme.
  • Stopping at the defects date. Items notified just before it stay open afterwards. Keep the register live until the certificate and the final assessment are done.

How this looks in Contract Status

A Defect with the Contractor's reply: fault, cause and action.

A Defect with the Contractor's reply: fault, cause and action. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Try the Supervisor role-play, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.