NEC Software vs Spreadsheets

For a single small NEC contract with one careful owner, a well-built spreadsheet can be enough. NEC software starts paying its way when you have several contracts, several people updating the record, or a level of change that makes reply dates easy to miss.

So the choice between NEC software and spreadsheets depends on the size of the job and who is keeping track. This comparison sits within the NEC contract management software guide, and is written for someone trying to decide, not for someone already sold.

Side by side

What you needSpreadsheetNEC software
Cost to startClose to nothingA subscription and setup time
FlexibilityChange any column todayYou work within the product's structure
Reply datesFormulas you write and have to trustWorked out from the periods you record
Telling the other sideSeparate e-mail or letterNotified when the record is submitted
Who changed whatLimited, and depends on your setupRecord history kept as a matter of course
Several people at oncePossible on shared files, but conflicts and overwriting are commonDesigned for it, with each side seeing its own actions
Other party's viewUsually a private list, or a copy sent outBoth sides see the same records, subject to access settings
Across many contractsManual roll-upBuilt-in lists across contracts
TrainingMost people already know spreadsheetsNew screens to learn
Getting the process rightDepends on the person who built itDepends on how well the product follows NEC, so test this

Where a spreadsheet is fine

  • A short contract with few expected changes.
  • One person owns the tracker, and is there for the whole job.
  • Notices already go out properly as letters or through an agreed system. The spreadsheet only tracks them.
  • You are clear that it is a private aid, and not the contract record.

If that is your position, spend your effort on the tracker. The guide to tracking NEC contracts in a spreadsheet covers how to build one that holds up.

Where spreadsheets tend to fail

The failures are rarely dramatic. A formula gets copied across a row with a Z-clause period, and nobody notices. A column labelled "date" means notified on some rows and aware on others, which is the difference that decides whether a 61.3 time bar applies. The tracker's owner goes on holiday. Two copies exist, and the one that went to the Client is three weeks old.

The other weakness is that a spreadsheet records what somebody typed about an event, not the event. If the question later is when a notice went out, the spreadsheet can't help on its own. You will be searching e-mails anyway. See tracking periods for reply for what needs to be captured.

Six signs it is time to change

  1. A reply date or a time bar has been missed, or nearly missed, because nobody saw it coming.
  2. The tracker depends on one person and you would struggle without them.
  3. You keep more than one version of the register and need to reconcile them.
  4. Producing the monthly report takes someone longer than a day, or involves re-keying.
  5. You run several contracts or mix NEC3 and NEC4, so one template's rules won't fit them all.
  6. When asked "what's waiting on us?", the honest answer is "let me check".

What software won't fix

Moving to software won't make a late notification on time if nobody told the commercial team, and it adds a discipline of its own: everyone has to use it, or the records stop matching what actually happened. A meeting decision or site instruction isn't on record until someone enters it.

In Contract Status, for instance, reply dates, Action Lists and history come from the records, but whether an event is a compensation event stays with you. Our audit trail guide covers what to keep either way.

If you are moving across

Don't try to load every closed row. Start with what can still cost you something: open compensation events and quotations, the current Accepted Programme, the live register, and the next assessment date. Keep the old spreadsheet read-only as a reference. If you think you are at that point, book a call, and bring the tracker along.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo