Skip to content
Book a demo

Avoiding Treated Acceptance by Keeping Replies on Time

Treated acceptance, often called deemed acceptance, happens when a Project Manager misses a reply, the Contractor notifies that failure, and there is still no reply after a further period. Deemed acceptance software can't remove that risk, but it can show every step coming, because this outcome takes two missed chances and at least two separate dates.

Nothing is ever treated as accepted automatically on the first missed reply. Knowing that changes how a Project Manager's team should work, and how a Contractor should use the right. This page covers the NEC4 ECC, with NEC3 differences. See the NEC contract management software guide for the wider picture.

How silence turns into a contract effect

Unanswered itemReply dueFurther period after the failure noticeWhat it is then treated asClause
Contractor's notification of a compensation event1 week, or longer if the Contractor agrees2 weeksIt is a compensation event, with an instruction to quote61.4
Quotation2 weeks2 weeksThe quotation is accepted, so the event is implemented on it62.3, 62.6
Project Manager's own assessment not madeThe time allowed for a quotation2 weeksThe Contractor's quotation is accepted64.3, 64.4
Programme, NEC4 only2 weeks1 weekThe programme is accepted31.3

These are the standard ECC periods, and your Contract Data or Z clauses may change them. Subcontract periods differ too, so use yours.

A few limits are often missed:

  • The notice is the Contractor's choice. Without it, the further period doesn't start and nothing is treated as accepted, though a late reply can still be a compensation event under 60.1(6).
  • A reply in the further period ends the route. The reply was late, but the matter isn't treated as accepted.
  • NEC3 has no such rule for programmes. A late reply is simply a compensation event. See deemed acceptance of a programme under NEC4.
  • Proposed instructions are different. A quotation for an instruction that hasn't been given isn't treated as accepted: NEC3 62.6 leaves it out, and NEC4 deals with proposed instructions separately in clause 65.

Why it deserves attention on the Client side

Take a fictional NEC4 Option A contract with illustrative dates. A quotation goes in on 6 May. The Project Manager's surveyor thinks it is too high, intends to instruct a revised quotation, and is pulled onto another job.

  1. 20 May. The reply date passes.
  2. 22 May. The failure notice arrives. It goes to the Project Manager, who assumes the surveyor has dealt with the quotation.
  3. 5 June. The further two weeks end with no reply. The quotation is treated as accepted.

The event is implemented on the Contractor's figures, so the change to the Prices and any movement of the Completion Date take effect. An implemented assessment generally stays as it is (66.3; 65.2 in NEC3), so the chance to answer it in the ordinary way has gone. There may still be a route through dispute resolution, but it has its own short limits: see time limits for NEC disputes.

Nothing dramatic happened in that story. Two people each thought the other had it. The fix is mostly about ownership.

What to track, whichever tool you use

DateWho should see itWhy
Reply dueThe person replying, and whoever covers themThis is the moment to answer, or to agree more time
Failure notice receivedThe Project Manager personally, and the commercial leadIt should never be routine. It means a further period is running
Last day of the further periodBoth sidesAfter this, the effect has arrived, and the next steps need recording
Agreement for more timeBoth sidesIt has to be agreed before the time runs out (61.4, 62.5, 13.5), so the date of the agreement matters

A system should treat the failure notice as a separate event with its own countdown. If the record only shows "overdue", the team can't tell a reply that's a day late from one that's about to become an accepted quotation.

In Contract Status, an overdue record offers the Contractor side the notice that the reply is late and then counts the period down. When it has run out, either side can record the deemed acceptance. It never gives the notice on the Contractor's behalf, because that decision is the Contractor's to make. Other systems will handle this differently, so run the same scenario on anything you are looking at, using the checks in how to choose NEC contract software.

Habits that reduce the risk on the Project Manager's side

  • Delegate properly. Under 14.2 the Project Manager can delegate actions after notifying the Contractor. A named delegate with cover is safer than an informal arrangement.
  • Answer what you can. A reply saying a revised quotation is needed, with reasons, is a proper reply. It doesn't need the final view on the money.
  • Ask early for more time. A Contractor who agrees a week today loses nothing, and it can't be fixed afterwards.
  • Review by reply date each week. A review by event number can hide the urgent item in the middle. Tracking periods for reply has a method.

And for the Contractor

Using the notice isn't sharp practice: the contract provides it. But the parties are also working in mutual trust and co-operation (10.2; part of 10.1 in NEC3), and a call first often gets a quicker and better answer than a formal route. If you do rely on a treated acceptance, keep the dates and the notice together on the record. See what to do when the Project Manager is silent on a quotation.

How this looks in Contract Status

A late reply in Contract Status: the banner, the clause and the button for the notice.

A late reply in Contract Status: the banner, the clause and the button for the notice. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Test your NEC knowledge, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.