Skip to content
Book a demo

A Defect Appeared After Completion: Who Fixes It?

The Contractor, if it really is a Defect and it comes to light before the defects date. For a defect after Completion under NEC, the defect correction period starts on the day it is notified, and the cost generally stays with the Contractor. What decides it is whether the item fails the Scope, or just wore out, got damaged or follows a Client's own design.

This page follows the NEC4 Engineering and Construction Contract (ECC), where notifying is clause 43.2 and correcting is 44.2. In NEC3, those are 42.2 and 43.2. The other side of this question is a defect after the defects date. Both sit under NEC questions answered.

Is it a Defect at all?

What has happenedLikely answerWho pays
Doesn't meet the Scope: pipes laid to the wrong fallDefectContractor, subject to the table further down
Contractor's design breaks the applicable law, or departs from its accepted designDefectContractor
Works as the Client's Scope required, but the Client's design was wrongNot a Defect, because it meets the Scope. A fault in the design in the Scope is a Client's liability under 80.1Client
Client's staff damaged it after take overNot a Defect. Damage to taken-over works is generally a Client's liability under 80.1Client
Wear from normal use, poor maintenanceNot a Defect, if it met the Scope when built. Check any performance or life requirement in the ScopeClient
Damage from a hidden fault that existed at take overThat exception in 80.1 puts it back with the ContractorContractor

The Defect definition sets the test. A Scope that requires a level of performance may make a failure in use a Defect, even when the installed product looks fine.

What to do, and the time limits

  1. Whoever finds it notifies. The Supervisor and the Contractor each notify a Defect as soon as they become aware of it, until the defects date. A Client or tenant who spots a problem should pass it to the Supervisor or Project Manager the same day.
  2. Work out the correction date. The period in the Contract Data runs from notification, and the Contract Data may give different periods for different kinds of Defect (see the defect correction period).
  3. Sort out access. If the part has been taken over, the Project Manager arranges for the Client to allow access and use, and the clock waits until these have been given (44.4). Record the date.
  4. Agree the cause if it isn't obvious. The Supervisor can instruct a search under 43.1 up to the defects date. If nothing is found, that is a compensation event for the Contractor under 60.1(10).
  5. Correct and close. Have the Supervisor confirm, and repeat any test that originally showed the problem.
  6. If it isn't fixed in time, go to the contractor won't fix a defect or, if access was the problem, no access to fix a defect.

Who bears the cost, by main Option

Main OptionCost of correcting after Completion
A and BThe Prices don't change. The Contractor absorbs it
C and DDisallowed Cost, whoever caused it within the Contractor's team
EDisallowed Cost as well
Any, with Option X15The position may change for a design Defect, if reasonable skill and care were used. See the X15 guide

The Contractor can look to its Subcontractor or designer under its own contract, but that doesn't delay the duty to the Client.

A fictional example

An office fit-out reached Completion on 1 April, with a 52-week period to the defects date and a four-week defect correction period. In September, the tenant reports water marks on a ceiling. The Supervisor inspects and notifies on 14 September that a pipe joint is leaking, which fails the Scope. The Contractor has until 12 October. The tenant allows access only from 21 September, so the period instead starts then, and the correction date moves to 19 October. Nobody disputes who fixes it. The tenant's replacement ceiling tiles and business interruption are a separate matter, and the contract's Defects clauses don't deal with them.

What you may hear

  • Contractor: "It's a maintenance issue." Then ask for evidence: when was it last serviced, and what does the O&M manual say? A search instruction may settle it.
  • Client: "You must fix it because you built it." Only if it is a Defect. Being the original builder doesn't make every later failure the Contractor's job.
  • Either side: "We'll get round to it." The contract has a period, so state the date in writing.

In practice, a short joint inspection within a few days does more than an exchange of letters. If the same Defect keeps returning, record each instance, since that may point to a design or system problem. For the whole process, see NEC quality and Defects.

How this looks in Contract Status

A Defect with the Contractor's reply: fault, cause and action.

A Defect with the Contractor's reply: fault, cause and action. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the NEC deadline calculator, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.