Actual Cost Came In Higher Than Our Accepted Quotation

No, you can't reopen it just because the job cost more. If actual cost is higher than your accepted quotation, clause 66.3 of NEC4 ECC (65.2 in NEC3) keeps the assessment as implemented, and any overrun falls according to your main Option.

What decides whether there's anything left to do is why it cost more. A wrong forecast stays as it is. A wrong assumption from the Project Manager, or a new and separate event, is different. For more problems of this kind, see the NEC questions section.

Check these before you give up

  1. Read the quotation and instruction again. Did the Project Manager state an assumption under 61.6 that has turned out wrong? If so, ask for a correction. It's an event under 60.1(17).
  2. Look for a new event. Did something else happen after your quotation? Notify it separately. The eight weeks under clause 61.3 is running on it.
  3. Look for a new instruction. Has the Scope changed again? Later changes are events of their own, under 60.1(1).
  4. Then take stock of your own position. If it's an overrun only, record the lesson and adjust how you forecast. Don't keep the argument alive by re-presenting it under another name.
  5. Early warn on the remaining work. If the overrun points to cost or delay yet to come, clause 15.1 may apply.

Who actually pays the overrun

Main OptionWhere the extra cost goes
A and BYou bear it. Your payment is based on the Prices, which don't rise
C and DDefined Cost is paid unless it's disallowed, but the target isn't raised. The extra feeds through the share calculation, so you and the Client each carry part
EDefined Cost plus Fee is paid unless disallowed, so the Client bears it. The accepted quotation changes the forecast, not what's paid

So on Option E, this question rarely hurts the Contractor, while on Option A it can. See how events work under Option A and under Option C.

What's still open, and what isn't

Why it cost moreOpen?
You under-forecast the work's durationNo
Your own productivity was lower than expectedNo
A subcontractor's price came in higher than quotedNo, unless a new event caused it
A risk you allowed for turned out largerNo. It's a forecast of a risk you carry
A stated assumption was wrongYes, through a correction
A new, different compensation event happenedYes, as its own event
You were asked to do something extraYes, through an instruction

A fictional example

Under Option A, a Contractor's accepted quotation for extra piling is £88,000, assuming the piling rig works five days. It takes eight days because of its own breakdown and a learning curve. Actual cost is £112,000. The £24,000 is the Contractor's; the assessment stands. Had the Project Manager's stated assumption been "ground as in borehole BH4", and the ground turned out different, the correction route would open on that difference.

Same job under Option C: the Contractor's paid the £112,000 plus Fee, but the target rose only by the quotation. The final target position takes the overrun into account.

How the other side will see it

A Project Manager asked to revisit an implemented event will refer to 66.3. It's a strong answer, and it works for both parties: the same clause protects you if the event comes in cheap. See actual cost less than quotation. It isn't unreasonable for them to say no; they're following the contract.

The contract's position is firm. In practice, if an event overran for a reason that really was out of your control, explain it early and look for what the contract actually offers. A general appeal to fairness gives the Project Manager nothing it can act on. To limit this next time, use risk allowances that are reasoned, and ask for assumptions when the unknown is too large. See quoting with unknown facts and what implementation means.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the NEC deadline calculator, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.