Skip to content
Book a demo

Our Permit Has Been Delayed: Who Takes the Risk?

It depends on who the contract made responsible for getting the permit: NEC has no clause on permits, so a permit delay is the Client's risk only if it fits a listed compensation event. The Scope usually settles who applies, and the Accepted Programme usually settles whether the delay counts.

That applies to a street works permit, an environmental consent, a planning condition or a possession. The numbers below are NEC4 ECC and the same in NEC3 unless stated. More live situations are in NEC questions answered.

What to do today

  1. Give an early warning. Do it now, whoever you think is responsible (15.1; NEC3 16.1). If you could have warned and didn't, any later event can be assessed as if you had.
  2. If you may have an event, notify it. You have eight weeks from becoming aware it has happened (61.3). Notify on the expected delay rather than waiting for the permit to arrive; the clause also covers an event expected to happen.
  3. Find who holds the job. Search the Scope, the Contract Data and any Z clauses for permit, consent, licence and approval.
  4. Look at the Accepted Programme. Note the date for the permit, as it stood when the delay began.

What decides it

The contract saysThe delay is caused byLikely route
The Client obtains and provides the permitLate provision against the Accepted Programme date60.1(3): a thing the Client was to provide came later than the programme showed. Without such a date, the event is harder to show
The Contractor obtains itA late or incomplete applicationContractor's risk, and no event
The Contractor obtains itThe authority taking longer than the programme showed, after a proper applicationPossibly 60.1(5), as Others not working within programmed times. This is arguable, so expect a challenge
The Contractor obtains it, for its own designThe authority won't approve the designContractor's risk. 27.1 puts approval of its design from Others on the Contractor
Nobody is named, and documents conflictGap or inconsistencyNotify under 17.1, and the Project Manager says how it is resolved. See gaps in the Scope
Permit refused for an event nobody could foreseeSomething neither Party could preventA narrow possibility under 60.1(19). It has to be something that stops the Contractor completing, or completing by the planned date, and that an experienced contractor would have judged too unlikely to allow for
The Client changes what is being built, needing a new permitAn instruction60.1(1), with the permit time included in the assessment

An authority counts as Others if it falls outside the people the contract lists, which include the Client. That matters where a public Client's own department issues the consent: ask whether that is the Client acting, or a separate statutory body.

Why the programme entry matters

The contract says a programme shows the dates when the Contractor will need things, including acceptances, items the Client provides and information from Others (31.2). Events 60.1(3) and 60.1(5) both look to times shown on the Accepted Programme.

In practice, if your programme shows a permit date as a line on the plan, with a realistic lead time, you have something to measure a delay against. If it shows nothing, or shows a date you knew was too short, your position is much weaker. A programme that assumes an unrealistically fast permit may also give the Project Manager a reason not to accept it.

Evidence to gather

  • The Scope extract and any information stating who applies.
  • The application, with its date, and proof it was complete.
  • The authority's published or stated turnaround, and its correspondence.
  • Early warnings and meeting records.
  • The Accepted Programme current at the time, and how the work has been held up.

Sample wording

Under clause 61.3 we notify an event we believe is a compensation event under clause [60.1(3) / 60.1(5)]. The Accepted Programme dated [date] shows [the permit] by [date]. As of today, it hasn't been provided, and [authority / Client] now expects [date]. This affects [activities]. We warned of this on [date]. We will provide a quotation when instructed.

What the other side is likely to say

  • "You should have allowed for that." Show the lead time in your tender programme and the authority's normal timescale.
  • "Your application was late or wrong." Have the dates ready. An event arising from the Contractor's fault gets no change to the Prices or dates (61.4).
  • If you are the Client: check who controlled the delay and whether the date was on the Accepted Programme before answering. Your reply to the notification is due within a week, and a missed answer can lead to treated acceptance (61.4).

How this looks in Contract Status

An early warning in Contract Status, with its risks, reply date and score.

An early warning in Contract Status, with its risks, reply date and score. See the worked example.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the NEC deadline calculator, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.