We Do Not Have Records for Our Defined Cost

You don't automatically lose the money, but you are exposed: with no records, Defined Cost is at risk, because cost your accounts and records don't justify is Disallowed Cost. What decides it is whether other evidence can still prove the cost was incurred, paid for and caused by the work.

The definition sits at 11.2(26) of Options C, D and E in the NEC4 Engineering and Construction Contract (ECC), and 11.2(25) in NEC3. Clause 52.2 lists what those Options expect you to hold. So start rebuilding now, because the Project Manager can inspect at any time in working hours (52.3). More on-site problems are in NEC questions answered.

What to do in the next two weeks

  1. Stop the gap growing. Find out why it happened, whether that is a person leaving, a system change or a Subcontractor who sends nothing. Fix that first.
  2. Size it. List by cost code and period what is missing. A gap of £20,000 is handled differently from one of £2m.
  3. Separate "not kept" from "not found". Search email, accounts systems, supplier portals and personal phones before you decide something is lost.
  4. Rebuild from the sources below, marking clearly which documents are reconstructions.
  5. Tell the Project Manager before the next application, if the sum is material. A disclosed reconstruction looks very different from one found during an audit.

Where evidence can come from

Missing itemNext-best sourceStrength
InvoiceDuplicate from the supplier; supplier statementStrong, once tied to a bank payment
Proof of paymentBank statements, BACS file, card records, remittance advicesStrong
TimesheetsPayroll, gate or biometric logs, induction and permit records, daily diariesGood when two or more agree
Plant on and off-hire datesHire company's records, delivery tickets, fuel records, telematics, dated photographsGood
Delivery ticketsSupplier's signed copies, quantities in the permanent worksGood for totals
Allocation of shared staffOrganisation charts, meeting records, emails showing what they didWeaker: expect a challenge and a lower percentage
Subcontract compensation event assessmentSubcontractor's copies, exchanges with it. 52.2 asks for these specificallyVariable

The line you can't cross

A reconstruction says what it is. A record made today and given last year's date, or a timesheet someone fills in now as if at the time, isn't a reconstruction. It could lead to allegations far worse than a disallowed sum, and NEC4 has its own rules about corrupt acts. Label each rebuilt document with the date it was prepared, who prepared it and what it was based on.

A fictional example

An Option C job, with illustrative figures. A site administrator leaves, and eight weeks of timesheets for a 12-person gang can't be found. Payroll shows £64,000 paid. Gate records show 11 of the 12 on site for most of those weeks, and the foreman's diary names the areas they worked in.

AmountBasis
Proved by payroll and gate records£58,500Two sources agree
Twelfth worker: payroll only£5,500Offered, but likely to be disallowed without more

The Project Manager accepts the first figure, and the Fee follows it. Disallowing the second costs the Contractor that sum plus its Fee. That may be an acceptable result: time spent on the rest may not be worth it.

How the Project Manager is likely to respond

The contract doesn't list which documents count as "accounts and records", beyond the items in 52.2 and whatever the Scope adds. So you can argue that reliable secondary evidence meets the test, and a reasonable reviewer may accept it. Equally, expect "these aren't the records you were told to keep", and a check on sample items. If you are told it's all out, ask for the reason on each line and see how to respond to disallowed costs.

Other main Options and compensation events

Under Options A and B, 52.2 and 52.3 don't apply, so there's no standing duty to show accounts. But if you are pricing a compensation event after the work, the Project Manager will expect support for the Defined Cost before the dividing date. Keep records of any event from the day it starts: clause 52 and the open book guide set out a sensible day-one system.

See how this works in practice

Click through Contract Status with sample contracts: raise the notice, reply to it, and watch both sides of one record.

Take the guided tour Book a demo

Use the NEC deadline calculator, use the free NEC tools or download free NEC templates.

This guide is general information in our own words, not legal advice. Your contract and its Contract Data always govern. NEC, NEC3 and NEC4 are trade marks of Thomas Telford Ltd; Contract Status is not affiliated with or endorsed by NEC.